kVAR
kVAR is a common meter label for kilovar, a unit of reactive power; 1 kvar equals 1,000 var. Read the sign, time basis, and meter convention with the value. An importing load can show negative kvar when its net behavior is capacitive. A reading in kvarh instead records reactive energy over time, and a low total power factor can persist when harmonic current remains after fundamental reactive power is corrected.
Kilovolt-amperes-reactive, the magnetizing power a capacitor supplies or a motor draws
Read the sign before diagnosing a negative value
Schneider Electric's ION meter guidance associates negative kVAR with a capacitive load and leading power factor under its stated IEEE sign convention. Apply that interpretation to the load's actual import/export state. A correction bank left connected after inductive loads stop can change the net reactive flow from lagging to leading without a meter defect.
Retain the meter's current-transformer direction, voltage-phase assignment, and import/export convention with the reading. Reversed sensing and actual capacitive operation produce different commissioning findings. Compare the phase values and operating state before interpreting a signed total in the EPMS record.
Use kvarh for accumulated reactive energy
Schneider Electric's unit-symbol guidance distinguishes kvar, a power, from kvarh, reactive energy accumulated over time. A steady 75 kvar for four hours accumulates 300 kvarh. It does not add 300 kWh of useful work to the active-energy register.
A demand reading also needs its interval. Compare a trend export and a demand register over the same start and end timestamps before calling the values inconsistent. An instantaneous 75 kvar screen capture cannot establish the interval average, and a cumulative kvarh register does not supply that average until its change is divided by the elapsed hours.
A 0.8 power factor does not mean 20 percent reactive power
Schneider Electric's Electrical Installation Guide limits the familiar power-triangle relationship to sinusoidal voltage and current. Under that relationship, a 500 kVA load at 0.8 power factor draws 400 kW and 300 kvar. Reactive power is 60 percent of apparent power in this case, because the components combine as perpendicular quantities rather than arithmetic percentages.
The same guide identifies P/S as displacement power factor for sinusoidal waveforms. With distorted current, total RMS current includes harmonic components, and subtracting kW squared from kVA squared does not necessarily isolate fundamental reactive power. Use the analyzer's defined reactive-power and displacement-power-factor channels when separating harmonics from a capacitor-correction problem.
Distinctions
- Capacitor nameplate kvar
- A bank's rated output is an equipment value at its stated electrical conditions. A service meter shows the net reactive flow at the metering point.
- kVA
- Apparent power describes the voltage-current loading. Reactive power is one component of that loading under the stated waveform model.
Frequently asked questions
Can kvar be zero while power factor is low?
Yes. Harmonic current can increase RMS loading while fundamental reactive power remains small. Compare total and displacement power factor.
Should the unit be kVAR or kvar?
Schneider's symbol guidance uses kvar and Mvar. Preserve a meter's channel label in exported records so its meaning remains traceable.