ANVILFIELD Try FieldOS

Field glossary · equipment

RPP

A remote power panel (RPP) divides a feeder into rack branch circuits, so its schedule needs both circuit positions and electrical capacity. Vertiv's Liebert RX combines 84 poles with a 400 A panelboard rating: the pole count describes space for breakers, not available amps at each rack. Monitoring adds separately configured circuit ratings and alarms. Keep the pole schedule, load calculation and alarm settings together when planning another rack connection.

Remote power panel, a panelboard fed from the PDU and placed near the rows to shorten branch runs

Used across 2 Anvilfield field guides, most in Datacenter.
Updated

How many circuits fit in an 84-pole RPP?

Vertiv lists its Liebert RX cabinet with 84 poles and a 400 A panelboard in a 24 x 12 in. footprint. Eighty-four poles do not mean 84 three-phase rack circuits. With compatible full-size three-pole breakers occupying three positions each, 84 positions accommodate 28 circuits before any other position use.

Maintain both the physical pole schedule and the electrical load schedule. A panel can run out of positions while carrying modest current, or retain empty positions while an existing feeder limits additional load. Reconcile the branch directory with that upstream relationship during PDU and RPP commissioning.

Monitoring starts with the right breaker configuration

Vertiv's Liebert RX user manual says the optional LDMF branch monitor is factory-configured for one-pole, 20 A breakers. Breaker names, ratings and alarm setpoints are field-adjustable. A newly fitted three-pole circuit therefore needs a corresponding monitoring configuration, even when its conductors and breaker are correctly installed.

Check that a multi-pole circuit is grouped under the intended circuit name and that its measured phases match the panel schedule. Otherwise, three currents can appear as three unrelated loads, or an alarm percentage can use the wrong current denominator. Keep the configuration export with the panel's turnover record. Vertiv's RX manual requires the panelboard power circuit to be de-energized and locked out before installing branch breakers or cables; a software change does not create that work boundary.

An overcurrent alarm is not the breaker trip curve

For the RX Current Plus Monitoring option, Vertiv publishes factory phase-current warning and overcurrent alarm setpoints above 75 and 80 percent of breaker amps, respectively. These are adjustable monitoring thresholds. They do not change the physical overcurrent device's time-current characteristic.

On a configured 400 A breaker basis, those percentages correspond to warning above 300 A and alarm above 320 A. The 320 A figure belongs to the display's alarm configuration. Compare protective behavior with the actual breaker and coordination record, and compare alarms with the monitoring configuration.

Distinctions

Floor PDU
A transformer-equipped floor PDU needs winding-ratio and tap records. An RPP needs feeder, branch and monitoring records without that transformer test scope.
Branch-circuit monitor
A monitor measures and reports the branch. The circuit breaker performs protection, so changing the monitor's rating entry does not uprate the breaker or conductor.

Frequently asked questions

Can an RPP be fed directly from a UPS?

Yes. In that arrangement, the RX monitoring percentages still use the configured breaker rating, not the upstream UPS kVA rating. Match the feeder voltage and protection to the panel and branch schedule before assigning capacity to another rack.

Does a 400 A RPP supply 400 A to every rack?

That is a panel-level rating. Each branch has its own breaker, conductor and connection ratings; available capacity also depends on existing load and the upstream path.

Sources checked

Where this shows up

Next step: Locate branch distribution work

Back to the full field glossary