ANVILFIELD Try FieldOS

Field glossary · data center

A and B feed

A and B feeds give equipment two supply paths, with the required separation defined upstream and the full operating load supported after either feed is removed. Their usable capacity is not the sum of both circuit ratings. Record three separate limits: the surviving electrical path, each equipment power supply's capability, and any contractual draw cap. A rack can satisfy one limit and exceed another.

Two independent power paths to one rack, each from a separate source, for redundancy

Used across 3 Anvilfield field guides, most in Datacenter.
Updated

Read the surviving capacity rather than adding two feeds

Vertiv's redundant rack PDU guidance budgets half of each PDU's capacity during normal operation when equal feeds share the load equally. That is a sharing assumption, not evidence that every server draws identical current from its two cords. A protection budget must also cover the operating modes in which a supply carries more of the load.

Equinix's power documentation determines a redundant AC pair's usable power from the voltage, current and phase of the primary circuit. The redundant circuit preserves that supply after a failure; it does not double the customer's usable allocation. Keep the pair together in the rack schedule so two installed receptacles do not become two independent capacity credits.

Separate the draw cap from the circuit rating

Equinix defines its Draw Cap as the total customer load across the deployment's circuits at any one time, measured in kVA. This contractual ceiling and the individual circuit's usable rating are different constraints. An installation with spare circuit capacity can still exceed its contracted allocation.

Equinix publishes 4.99 kVA of usable power for its AMER 208 V, single-phase, 30 A circuit configuration, equivalent to about 24 A usable current. At matching voltage and power factor, a rack drawing 2.1 kVA on A and 1.5 kVA on B totals 3.6 kVA. The survivor must supply about 17.3 A, leaving about 6.7 A below that circuit's usable limit. Enter 3.6 kVA against the deployment Draw Cap and 17.3 A against the surviving circuit; the contract and circuit checks use different units.

What the A/B evidence should distinguish

Build a connection record that identifies the equipment supply, rack outlet, outlet bank, branch circuit and upstream failure boundary. Include the measured loading condition and whether the equipment was sharing power or using an active and standby arrangement. Those details explain why normal A and B readings differ and identify which limit applies to the transferred load.

Installed circuits, normal draw, surviving capability and purchased capacity belong in separate schedule fields. In the PDU commissioning schedule, give each equipment connection an A-path and B-path identifier. Use the outlet and bank identifiers from the selected rack PDU assembly so the upstream limit can be traced from the equipment cord.

Distinctions

Two power supplies
Duplicated equipment supplies address a supply failure. The upstream feeds and the surviving supply capacity determine what happens after an electrical path is lost.
2N
A topology description addresses duplicated system capacity. A/B labels alone do not establish the extent of that duplication.

Frequently asked questions

Does A/B power provide twice the usable rack power?

For a redundant pair intended to sustain the same load after either circuit is lost, allocate the load against the surviving path and the contractual limit.

Should the A and B meter readings always be equal?

No. Sharing behavior and equipment populations affect the split. Retain both readings and the equipment operating mode when documenting the load.

Sources checked

Also defined as

  • Two strips on two independent paths for redundant power to one rack

Where this shows up

Next step: Track power upgrade bids

Back to the full field glossary