Ton of refrigeration

Calculate delivered refrigeration tons on a plain-water circuit as gpm × temperature drop in °F / 24, using DOE FEMP's water approximation. At 240 gpm and a 9°F drop, the result is 90 tons. NIST's equivalent unit values are 12,000 Btu/h and approximately 3.516853 kW of heat removal per ton. Electrical input remains a separate measurement; sensor bias at a small temperature difference can distort both reported capacity and kW/ton.

12,000 BTU per hour of cooling, about 3.516 kW, the heat to melt a ton of ice in a day

Used across 2 Anvilfield field guides, most in HVAC.
Updated

The 500 factor belongs to the fluid

DOE FEMP's Example M&V Plan calculates water-side cooling tons as gpm × 500 × entering-minus-leaving water temperature in °F, divided by 12,000. The familiar divisor 24 is the ratio 12,000/500. This equation needs the flow through the same boundary as the two temperature readings.

Trane's Chilled-Water Systems clinic explains that 500 combines water density, specific heat and the conversion from minutes to hours; antifreeze mixtures change that factor. Enter the fluid's concentration and properties at operating temperature when calculating glycol-loop capacity. A water equation applied unchanged to another fluid creates a systematic error, even with perfect instruments.

Using the FEMP water approximation, 240 gpm through an evaporator with a 9°F drop delivers 90 tons. That is about 316.5 kW of thermal output using NIST's conversion. Neither result states the compressor's electrical demand. The chiller selection guide supplies the equipment-performance context.

Low-load cooling magnifies temperature-sensor bias

Applying DOE FEMP's water-side equation, a 0.4°F differential-temperature bias on a true 3°F drop overstates cooling by 13.3 percent when flow is correct. At the same 240 gpm, the true result is 30 tons, but a reported 3.4°F drop produces 34 tons. The bias is the error in the difference between sensors, not necessarily the error of either sensor alone.

At a true 10°F drop, the same 0.4°F error changes capacity by 4 percent. This comparison explains why low-load efficiency trends need particularly good agreement between supply and return sensors. A sensor pair that looks adequate against a large temperature span can distort a small one.

The efficiency error runs in the opposite direction. With a measured 24 kW input, the actual 30-ton result is 0.80 kW/ton; dividing by the biased 34 tons reports about 0.71 kW/ton. Nothing in that apparent improvement requires the compressor to perform better. Correct the measurement before attributing the change to plant tuning.

Keep bypass flow outside an evaporator-only calculation

Draw the measurement boundary on the piping diagram. A common-header meter includes every active flow path through that header, while an individual evaporator's temperature drop belongs only to that evaporator. Multiplying the combined flow by one machine's drop assigns cooling to water that did not pass through it.

Trane notes that flow-meter accuracy depends on the instrument's usable flow range and the pipe-flow profile at its installation. Save the meter location and operating range with the sensor locations, fluid data and synchronized readings. Carry that record into capacity verification, where another technician can reproduce the boundary and calculation.

Tons measure capacity; ton-hours measure cooling energy

Using NIST's refrigeration-ton conversion over one hour, a ton-hour equals 12,000 Btu or approximately 3.516853 kWh of thermal energy. An ice-storage schedule in ton-hours describes accumulated cooling, while a chiller selection in tons describes the rate available to meet load.

A plant holding 90 tons for four hours supplies 360 ton-hours, about 1,266.1 thermal kWh. Its capacity during that period is still 90 tons. For a changing load, sum each measured ton value multiplied by its time interval; multiplying the peak tonnage by the entire operating shift overstates the total whenever the plant unloads.

Distinctions

Displayed load percentage
A controller's percentage requires its own definition and capacity basis. It is not a substitute for measured thermal output across the selected water-side boundary.
Ton-hour
Cooling energy accumulated over time. Multiply refrigeration tons by operating hours, keeping the thermal result separate from the electric meter reading.

Frequently asked questions

Can pump speed alone tell me the delivered cooling tons?

Speed establishes neither measured flow nor temperature drop. Cooling output needs both, along with the fluid properties for the loop being measured.

Why did my calculated tons improve after replacing a sensor?

Review the old and new differential-temperature readings at comparable load. Removing sensor bias changes reported capacity even when the actual heat transfer stays the same.

Sources checked

Also defined as

  • 12,000 BTU per hour of cooling; the unit a chiller's capacity is rated in

Where this shows up

Next step: Map tower-served facilities