IEEE 142: Green Book grounding references and resistance-grounded systems

The Green Book, IEEE 142, addresses industrial and commercial system grounding, equipment grounding, connections to earth, static electricity, lightning, and electronic-equipment grounding. IEEE 142-2007 is its latest published edition and is inactive-reserved. Its broad subject matter now requires a more specific reference selection: source-neutral grounding, equipment bonding, and electrode-system measurements are different engineering questions, even when an older specification cites the same Green Book for all three.

Current edition: IEEE 142-2007 (2007; inactive-reserved)
Updated

Official publisher page

Applies to

Electrical designers use the Green Book background when comparing grounded, ungrounded, and impedance-grounded systems. Contractors and testing firms encounter it in legacy grounding specifications, especially where a plant has a neutral-grounding resistor or an older grounding design report.

Start a legacy Green Book work order by naming its acceptance object: the source-neutral arrangement, equipment bonds, earth electrodes, or HRG monitoring functions. The ground resistance testing guide addresses the electrode measurements. A neutral resistor's nameplate and alarm test answer separate questions that the earth-resistance result cannot settle.

Key topics

Map Green Book subjects to individual 3003 documents

IEEE 3003.1-2019 is the active recommended practice for system grounding. IEEE 3003.2-2014 covers equipment grounding and bonding, but IEEE identifies that publication as inactive-reserved since March 27, 2025. The 3000-series number alone therefore does not prove an active replacement. A reference register should show both the task covered and the status of each selected document.

Ground-fault amperes and electrode ohms describe different things

Eaton's March 2025 TD019001EN lists 5 A and 10 A tapped neutral resistors for its low-voltage HRG equipment. Post Glover's HRG application guide distinguishes that resistor current from total fault current, which also includes the system's capacitive contribution. Neither current rating is an electrode-resistance target. Put the source voltage, resistor tap, thermal duty, and charging-current basis on the design schedule, with earth-electrode acceptance recorded separately.

Phase-to-neutral loads affect the HRG application

Eaton's March 2025 data cites the 2023 NEC 250.36(3) prohibition on line-to-neutral loads supplied by the resistance-grounded system. Its drawing supplies those loads through a separate delta-wye transformer. During a retrofit review, trace lighting, controls, and auxiliary loads as well as the large three-phase motors; a usable source neutral alone does not establish that the distribution arrangement meets this application condition.

Grounding acceptance includes alarm and resistor condition

Eaton describes ground-fault indication, alarm contacts, a test function, and neutral-resistor health monitoring for its HRG equipment. Record which functions the furnished system includes and the approved functional evidence for each. An electrode test cannot establish that a resistor is intact, an alarm reaches the attended location, or the source-neutral connection matches the one-line.

How it is used in the field

For a solid phase-to-ground fault on a 480 V wye source, approximately 277 V appears across the neutral resistor. A 5 A resistive contribution requires about 55.4 ohms and dissipates about 1.39 kW, using V ÷ I and V × I. Those results describe the resistor under that fault condition. Its continuous or time-limited thermal rating must match the specified duty, and total fault current also includes the capacitive contribution.

An HRG equipment submittal should identify the source winding, grounding-transformer arrangement where used, resistor current and duty, monitoring scheme, and fault indication. Reconcile those details with the plant's actual load connections. A test sheet headed only 'IEEE 142 ground test' does not tell the reviewer whether it documents an electrode measurement, a continuity check, or a functional test of the source grounding equipment.

During a plant modification, preserve the original grounding design assumptions and identify the change in connected feeders, transformers, or operating ties. That gives the designer a defined configuration to review. The power QA guide supplies the surrounding acceptance workflow; the grounding package should establish the installed grounding arrangement and the behavior demonstrated for it.

Edition history

IEEE 142-2007 superseded IEEE 142-1991 and was published November 30, 2007. IEEE records March 25, 2021 as its inactivation date. The Green Book remains an identifiable historical reference, while the status of each related 3003 publication is checked individually.

Adoption

A project specification establishes where a Green Book reference is used. Installation code requirements follow the jurisdiction's adopted edition, while the source-grounding design identifies the actual connection and equipment duty. Eaton's 2023 NEC cross-reference should retain that edition when quoted in an engineering review.

Frequently asked questions

Is IEEE 3003.2-2014 an active replacement for the Green Book?

It covers equipment grounding and bonding, but IEEE lists it as inactive-reserved. IEEE 3003.1-2019 is active and covers system grounding. Choose the document by subject and record its actual status.

Does a 5 A grounding resistor mean a 5-ohm ground?

The current is the source-neutral resistor design value. Resistor ohms follow from the applicable voltage and current; earth-electrode resistance is a separate measurement with a separate acceptance basis.