ANVILFIELD Try FieldOS

Electrical

Pull and junction box sizing with NEC 314.28 for electrical crews

Size the pull box from the conduit geometry, not the conductor count, so the big conductors have room to pull and bend without damage before the cover goes on.

Pull BoxNEC 314.28Junction BoxConductor BendingElectrical

Direct answer

Pull and junction box sizing under NEC 314.28 sets minimum dimensions from conduit geometry so large conductors can be pulled and bent without damage. For conductors 4 AWG and larger, a straight pull needs a length at least 8 times the largest raceway trade size, an angle pull at least 6 times. The adopted code edition and AHJ govern.

On this pageWhat a pull box does, and why it gets sized by the conduitWhat is the difference between box fill and pull box sizing?When does NEC 314.28 apply?What is the 8 times rule for pull boxes?The angle, U, and splice pull ruleThe distance between raceway entriesField example: a 3-in conduit straight throughField example: an angle pull with three conduitsWhy the rules exist: bending radius and pulling roomSplices and connections inside the boxDoes a junction box have to be accessible?Wireway and auxiliary gutter vs a pull boxWhen do you need a pull box?How the conduits land in the boxGrounding and bonding in the boxLarge feeders, service conductors, and the data-center pull boxBox types and enclosure ratingsLaying out the box before you order itWhat to documentCommon mistakesField checklistStandards and referencesUnits, terms, and conversions

Key takeaways

  • NEC 314.28 sizes pull and junction boxes from conduit geometry, not conductor count, for conductors 4 AWG and larger.
  • Straight pull: box length must be at least 8 times the trade size of the largest raceway entering the box.
  • Angle, U, and splice pulls: distance to the opposite wall must be at least 6 times the largest raceway plus the sum of the others in that row.
  • Distance between two raceways carrying the same conductors must be at least 6 times the larger raceway's trade size.
  • A pull run is limited to 360 degrees of bend (four quarter bends) between pull points, and boxes must stay accessible without disturbing the structure or finish.

What a pull box does, and why it gets sized by the conduit

A pull box, or junction box, is the enclosure where conductors are pulled through, spliced, or routed from one raceway into the next. On a long or bending run, you cannot pull heavy conductors the whole distance in one shot, so the box is the point where you stop, feed, and re-pull. It is also where feeders split, where a splice lands, and where a direction change happens that the conduit cannot make on its own.

Here is the part that trips up people who only know box fill. A pull box for large conductors is not sized by counting wires and adding cubic inches. It is sized by the conduits entering it and the path the conductors take through it, so the box is big enough to pull and bend the conductors without kinking the insulation or overstressing the copper. The box has to give room to pull and bend, not just hold the conductors.

NEC 314.28 is the rule that sets those dimensions. Box fill, the cubic-inch count for small device and outlet boxes, lives in 314.16 and is covered in the box-fill guide. The raceways feeding the box, their support and their bend limits, are covered in the wiring-methods guide. This guide is the box in the middle, sized so the big conductors survive the pull.

What is the difference between box fill and pull box sizing?

Box fill and pull box sizing are two different calculations for two different problems, and using the wrong one is the most common sizing mistake on the job. Box fill, under NEC 314.16, counts the conductors, devices, clamps, and grounds inside a small outlet or device box and totals the cubic inches so the wires are not crowded. That is a crowding calculation for small boxes, and it is the subject of the box-fill guide.

Pull box sizing, under NEC 314.28, ignores the cubic-inch count entirely and works from geometry. It asks how the conductors enter, how they leave, and whether the box is long enough and wide enough to pull and bend them. It applies to the larger boxes that handle big conductors and multiple raceways, where bending radius and pulling tension, not crowding, are what damage the conductors.

The short version of the distinction: 314.16 is about how many conductors fit by volume, 314.28 is about whether the large conductors can physically be pulled and bent in the space without harm. A small device box gets the fill calculation. A feeder pull box gets the geometry calculation. They are not interchangeable, and a box that passes one can fail the other.

When does NEC 314.28 apply?

NEC 314.28 applies to pull boxes, junction boxes, and conduit bodies used with conductors 4 AWG and larger. That conductor size is the trigger. Below 4 AWG, the box is generally sized by the box-fill rules in 314.16, because the conductors are small enough that crowding, not bending radius, is the limiting factor. At 4 AWG and larger, the conductors are stiff enough and the pulling tension high enough that the geometry rules take over.

The threshold is about the conductor, not the box. A junction box on a small lighting circuit follows box fill. The same physical box, if you route 1/0 feeders through it, falls under 314.28 because the conductor crossed the 4 AWG line. The rule applies regardless of system voltage, and for installations over 1000 V there is a separate, larger set of requirements, commonly found at 314.71, that you size to instead.

Confirm the exact wording and the conductor threshold against the adopted code edition, since the section organization and the cutoff have been refined across cycles. The 4 AWG trigger has held for a long time, but the AHJ and the adopted edition control, and a conduit body has its own related provisions you check alongside the box.

What is the 8 times rule for pull boxes?

The 8 times rule is the straight-pull requirement in NEC 314.28. For a straight pull, where conductors enter one wall and leave the opposite wall in a straight line, the box length in the direction of the pull must be at least 8 times the trade size of the largest raceway entering the box. That length is what gives the conductors room to come in, travel, and feed out without a bend tight enough to damage them.

Only the largest raceway sets the multiplier on a straight pull. If a 3-in conduit and a 2-in conduit both run straight through, you size on the 3-in: 8 times 3 is 24 in of minimum length. The smaller conduits riding alongside do not add to a straight-pull length the way they do on an angle pull. The width and depth of the box are sized separately, for the locknuts, bushings, and the other raceways on the wall.

The 8 multiplier is the figure in current editions for the straight pull, but treat the number as code-driven and verify it against the adopted edition. The point behind it does not change between cycles: a straight pull needs eight diameters of length so the conductor is not jammed and kinked on its way through.

The angle, U, and splice pull rule

When the conductors change direction in the box, the straight-pull rule no longer fits, and 314.28 uses a different distance. For angle pulls, U pulls, and pulls where the conductors are spliced, the distance from each raceway entry to the opposite wall must be at least 6 times the trade size of the largest raceway in that row, plus the sum of the trade sizes of the other raceways in the same row on the same wall.

The 6x-plus-the-rest structure matters. On an angle pull you take six diameters of the largest conduit for the bend itself, then add the diameters of every other conduit sharing that row, because those conductors all have to make the turn in the same space without crowding each other. A U pull, where conductors enter and leave the same wall, is handled the same way as an angle pull. A splice in the box is treated like a direction change for sizing, because the spliced conductors need the same room.

The 6 multiplier on the largest plus the others is the figure in current editions. As with the straight pull, treat it as code-driven and confirm it against the adopted edition. The reason it runs smaller than 8 is that a turning conductor uses the diagonal of the box, so the box can be shorter in any one direction and still give the conductor its radius.

The distance between raceway entries

There is a third dimension 314.28 controls that crews forget, and it is the one inspectors check on angle pulls: the distance between the two raceway entries that enclose the same conductor. That distance, measured between the raceways, must be at least 6 times the trade size of the larger of the two raceways.

This rule keeps a conductor from making too sharp a turn between where it enters and where it leaves. You can satisfy the 6x distance to the opposite wall and still bunch the entry and exit conduits too close together, forcing the conductor into a bend tighter than its insulation tolerates. The entry-to-entry distance is the check that catches that. For two 3-in conduits carrying the same conductors, the entries need at least 6 times 3, or 18 in, between them.

On a box with several angle pulls sharing walls, you run this check for every pair of conduits that carry the same conductors, not just the worst pair. It is easy to lay out a box that passes the wall distance and fails the entry spacing on one pair buried in the middle. Verify the multiplier against the adopted edition, but plan the conduit entries with this distance in mind before you punch the box.

Field example: a 3-in conduit straight through

Take the simplest case. A pull box has a single 3-in conduit entering one wall and a single 3-in conduit leaving the opposite wall, conductors running straight through, 350 kcmil copper feeders that are well past the 4 AWG trigger. This is a straight pull, so the 8 times rule sets the length.

Largest raceway is 3 in. Box length in the direction of the pull is 8 times 3, which is 24 in minimum. That is the dimension between the two walls the conduits enter. The other two dimensions, the width and the depth, are set by what it takes to land the locknuts and bushings and to get the conductors turned in, not by the pull formula, so a common box might end up 24 in long by 12 in or so the other way, sized to the fittings.

Round up to a standard box size at or above the calculated minimum. You never go under the calculated dimension to fit a stock box. If the only box on the shelf is 20 in long, it does not pass, and pulling 350 kcmil through a box two-thirds the required length is how insulation gets scraped on the conduit end. Order the box to the number, not the number to the box.

InputValue
Pull typeStraight pull
Largest raceway3 in trade size
Conductors350 kcmil Cu (over 4 AWG)
Rule8 x largest raceway
Minimum length8 x 3 = 24 in
Width and depthSized to fittings and turn-in

Field example: an angle pull with three conduits

Now an angle pull. One wall of the box takes three conduits in a single row: one 3-in, one 2-in, and one 2-in. The conductors turn 90 degrees inside the box and leave through an adjacent wall. The 3-in is the largest in the row, so it sets the 6x base, and the other two add their trade sizes on top.

Run the angle formula: 6 times the largest, plus the sum of the others. That is 6 times 3, which is 18, plus 2 plus 2, for 22 in minimum from that row of entries to the opposite wall. Notice the smaller conduits each added their full trade size, not a multiple of it. If a fourth conduit shared that row, you would add its trade size too.

Then run the entry-distance check for any pair of conduits carrying the same conductors, at 6 times the larger of the pair. The governing box dimension is whichever of these comes out largest across all the pulls and all the walls. On a real box you size every wall this way and take the worst case for each direction, because one undersized wall fails the whole box.

InputValue
Pull typeAngle pull, one row
Raceways in row3 in, 2 in, 2 in
Largest in row3 in
Rule6 x largest + sum of others
Calculation(6 x 3) + 2 + 2 = 22 in
Then also checkEntry-to-entry, 6 x larger of pair

Why the rules exist: bending radius and pulling room

The multipliers are not arbitrary. They exist so a large conductor has the room to bend at its minimum radius and the room to be pulled without the insulation dragging hard on the edge of a conduit. A 500 kcmil conductor does not turn on a dime. Force it around a corner tighter than its bending radius and you crack the insulation, deform the strands, or both, and the damage is inside the box where nobody sees it until it faults.

Pulling tension is the other half. When you pull heavy feeders, the conductor is under real load, and a box that is too short means the conductor exits the conduit and immediately hits the far wall or makes a sharp turn while it is still moving under tension. That is when the jacket gets scraped to the copper. The 8x and 6x distances buy the slack and the angle the conductor needs to come out, line up, and feed on without abuse.

Box depth plays into this too. The box has to be deep enough that the conductors clear the cover and have room to lie without being mashed against it, and deep enough for the locknut and bushing on each conduit to land. A box that satisfies length and width but is too shallow still crowds the conductors against the cover, which is its own way of damaging insulation.

Splices and connections inside the box

When conductors are spliced in the box rather than pulled straight through, the box has to hold the splice with room to spare, and the splice itself is sized as if it were a turning conductor. A spliced pull is treated like an angle pull for the dimension rules, because the spliced conductors and their connectors need the same bending and working space a direction change does.

The box also has to leave room for the splice hardware. Split-bolt connectors, mechanical lugs, insulated multi-tap blocks, and the tape or covers over them all take space the bare conductor did not. On large feeders the connector can be the bulkiest thing in the box, and a box sized only for the conductors will not close over the finished splice. Lay out the splice volume, not just the conductor path.

There is also a limit on how much of the box cross-section the splices, taps, and conductors can fill at any one point. The wiring space cannot be so packed that you cannot work the conductors. Power distribution blocks and similar gear mounted in the box have their own clearance and wire-bending-space requirements you check against the listing and the applicable code section.

Does a junction box have to be accessible?

Yes. A pull box or junction box has to remain accessible without taking apart the building or disturbing any part of the structure or finish. You cannot bury it behind drywall, tile it over, or pour it into a slab and call it done. The whole point of the box is that someone can open it later to inspect a splice or re-pull a conductor, and a box plastered into a wall defeats that.

This is a frequent inspection failure and a frequent field cheat. A junction box gets covered by a later trade, or somebody hides an ugly splice above a hard ceiling with no access panel. The code wants the cover reachable. If the box is above a lift-out ceiling, that usually counts as accessible. If it is above hard-lid drywall with no panel, it does not.

The cover itself has to suit the box and the location. Every box needs a cover, a faceplate, or a fixture canopy, and it has to stay in place. In a wet or damp location the cover and the box have to be rated for it. Marking helps the next person: where conductors of different systems or circuits share a box, identifying the circuits inside saves the troubleshooter from guessing, and some installations require that identification.

Wireway and auxiliary gutter vs a pull box

A wireway, sometimes called an auxiliary gutter when it sits next to equipment, is a long sheet-metal trough with a removable cover that carries conductors and lets you tap or splice along its length. It is not the same thing as a pull box, and it is sized by a different rule. People reach for a wireway when they have many conductors running a common path and need to make taps, not when they are turning a couple of large feeders through a box.

Where a pull box is sized by the 314.28 geometry, a wireway is limited by a conductor fill, commonly 20 percent of its cross-sectional area, with its own rules for splices and taps and for derating when too many current-carrying conductors share the trough. The wireway and auxiliary gutter articles, separate from 314, govern those.

Even so, the pull rules follow the conductors. Where a raceway connects to a wireway and the conductors make an angle pull or a U pull, the same bending-distance logic applies at that point. So a wireway can still owe you a 6x distance at a turn even though its length is governed by fill, not by the 8x rule.

When do you need a pull box?

You need a pull box wherever a conduit run has too many bends or runs too long to pull the conductors through in one go. The code limit that forces this is the bend rule: between pull points, a conduit run is held to no more than the equivalent of four quarter bends, 360 degrees total. Hit 360 degrees of accumulated bend and you have to break the run with a pull point, which is usually a pull box or a conduit body.

The reason is pulling tension again. Every bend adds friction, and past about 360 degrees the tension to pull the conductors climbs high enough to damage them or to make the pull impossible. The bend rule lives in the individual raceway articles, EMT, rigid, PVC, and the rest, and it is covered in the wiring-methods guide. The practical effect is that a long run with several turns gets pull boxes spaced so no single segment exceeds the limit.

Field crews also add pull points beyond the code minimum to make a hard pull easier, especially on long straight runs of large conductor where 360 degrees was never the issue but friction over distance was. A box every so often on a long feeder run turns one brutal pull into two manageable ones. Plan the pull points with the conduit layout, not after the pipe is in.

How the conduits land in the box

Every raceway entering the box has to be secured and terminated so the box and the conduit support each other and the conductors are protected at the entry. On threaded rigid and IMC that is a locknut inside and out with a bushing on the conductor side. On EMT it is the connector for the method. The bushing matters most where the conductors are 4 AWG and larger, because an unprotected metal conduit end will cut the insulation as the conductor flexes against it.

The box and the conduits both need support. A heavy pull box full of large feeders is not held up by the conduit stubs alone. It gets its own support sized to its weight, and the conduits get their support within the distance their article allows of the box. The support intervals by method are in the wiring-methods guide.

Where the conduit is metal and serves as part of the grounding path, the connections have to be made up tight and bonded so that path is continuous through the box. Concentric or eccentric knockouts, reducing washers, or a painted surface can interrupt that path, so bonding fittings or bonding jumpers go in where the standard connection cannot be trusted to carry fault current.

Grounding and bonding in the box

The equipment grounding conductors and the metal of the box have to be bonded together so fault current has a continuous path back to the source. In a metal box with metal conduit, that path runs through the conduit, the fittings, and the box, which is why the fittings have to be tight and the knockouts intact. Where anything breaks that metallic path, you bond around it.

Where conduits enter through oversized, concentric, or eccentric knockouts, the standard locknut may not bite enough metal to carry fault current reliably, so bonding bushings and bonding jumpers are used to guarantee the connection. On service-side equipment and where the available fault current is high, the bonding is held to a higher standard than on the load side, and the bonding means are specified accordingly.

The equipment grounding conductors passing through or spliced in the box get joined so the path stays continuous, typically to a grounding terminal or lug provided for the box. If the phase conductors were upsized for voltage drop or any other reason, the equipment grounding conductor may have to grow in proportion, which is covered in the voltage-drop work. The box is where that grounding conductor often lands, so it is where the size gets verified.

Large feeders, service conductors, and the data-center pull box

The biggest pull boxes show up on service entrances, large feeders, and high-density work like data centers, where parallel sets of large conductors run together and every set has to be pulled and turned without damage. With parallel conductors, the conduits multiply fast, and an angle pull on a wall full of 4-in conduits drives the box dimensions up quickly under the 6x-plus-the-rest rule.

Pulling tension on these is real work. Large conductors are heavy and stiff, the pulls are long, and the box is where the conductor is most vulnerable as it comes out under load. This is exactly where an undersized box scrapes a 600 kcmil conductor on the conduit end or forces it into a radius the insulation will not take. Size to the geometry, then add margin on the hard pulls.

On parallel runs there is a further wrinkle: the conductors of each parallel set should be grouped and kept to similar lengths and arrangement so the current divides evenly between them. A pull box is where that grouping gets organized, so lay the box out with enough room to keep each set together and dressed, not just enough to meet the minimum dimension.

Box types and enclosure ratings

Pick the box construction and rating for the location, the same way you pick the wiring method. Indoors in a dry, clean space, a standard sheet-steel box with a screw cover is the usual choice. Outdoors, in a washdown area, or anywhere water or dust is a factor, the box and its cover have to carry the right enclosure rating for the exposure, and the conduit entries have to keep that rating with the proper fittings.

Enclosure ratings are commonly given as NEMA types: a general indoor box is one class, a raintight outdoor box is another, and a washdown or corrosive environment calls for a sealed, sometimes stainless or nonmetallic, enclosure. The rating only holds if the whole assembly keeps it, so a raintight box with a knockout left open or a non-rated fitting is no longer raintight. Match the fittings and the cover gasket to the box rating.

Listing matters as much as size. Use a box listed for the use, sized to the 314.28 geometry, and rated for the location. A box that meets the pull dimensions but is the wrong type for a wet location will pass the math and fail the environment, and the failure is corrosion and water in the splices a year later.

Laying out the box before you order it

Size the box from the conduits before anything gets ordered or punched. Lay out where each raceway enters, group them by wall and row, identify which pulls are straight and which are angle or U, and mark which conductors are spliced. That layout is what feeds the 314.28 math, and doing it on paper or in the model is far cheaper than discovering an undersized box after the pipe is stubbed into it.

Run the worst case for each dimension. The straight pulls give you minimum lengths in their direction, the angle pulls give you 6x-plus-the-rest distances, and the entry-to-entry checks catch the tight conduit pairs. The box has to satisfy the largest result in each direction, so take the governing number per dimension and round up to a standard box at or above it.

The estimate and the install part ways right here if nobody does this. The takeoff assumed a stock junction box, the field laid out the real conduit entries and found the box has to be a foot longer, and the difference is a change order or eroded margin. Catch the box size at layout, with the conduit plan in front of you, not when the conductors will not pull.

What to document

A pull box that meets 314.28 should leave a record of how it was sized, because the next person to open it or to inspect it will want to see the math, not take it on faith. The record is also what defends the box if an inspector questions a dimension or a future renovation adds conduits to a wall that was already at its limit.

Capture each wall: the raceways entering, their trade sizes, whether the pull is straight or angle or splice, the rule applied, the calculated minimum, and the box dimension provided. Note the entry-to-entry checks where they governed. Record the box type and enclosure rating for the location and that it lands accessible. The table below is the shape of that record, one row per pull, so a reviewer can reproduce every dimension.

Pull typeRuleExample
Straight pull8 x largest raceway8 x 3 in = 24 in length
Angle or U pull6 x largest + sum of others in row(6 x 3) + 2 + 2 = 22 in
SpliceTreated as angle pull6x distance plus splice room
Entry to entry (same conductors)6 x larger of the pair6 x 3 in = 18 in apart

Common mistakes

  • Using the 314.16 box-fill cubic-inch count to size a box for conductors 4 AWG and larger instead of the 314.28 geometry.
  • Undersizing the box so the large conductors have no room to pull or bend, scraping insulation on the conduit end.
  • Forgetting the rules entirely and grabbing a stock box, missing the 8x straight or 6x angle minimum.
  • Sizing only on the largest raceway for an angle pull and skipping the sum of the other raceways in the row.
  • Ignoring the entry-to-entry distance between raceways that carry the same conductors.
  • Burying or concealing a junction box behind a hard ceiling or wall with no access.
  • Running past 360 degrees of bend with no pull box, making the pull impossible or damaging the conductors.
  • Using a box that meets the dimensions but carries the wrong enclosure rating for a wet or corrosive location.

Field checklist

0 of 10 complete

Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.

Standards and references

The NEC, NFPA 70, is where the rules live. Pull and junction box sizing for conductors 4 AWG and larger is in Article 314, commonly at 314.28, which gives the straight-pull, angle-pull, U-pull, and splice distances and the entry-to-entry spacing. Box fill, the cubic-inch count for smaller boxes, is at 314.16 and is the subject of the box-fill guide. Installations over 1000 V follow a separate, larger set of requirements commonly found at 314.71.

The bending and pulling space at terminals inside equipment, as opposed to the pull-through distances, is governed elsewhere, with Table 312.6 commonly cited for wire-bending space at terminations. The 360-degree bend limit between pull points lives in the individual raceway articles in Chapter 3, covered in the wiring-methods guide. Wireways and auxiliary gutters have their own articles with a fill rule rather than the 314.28 geometry.

Treat the multipliers, the 8x and the 6x, and the 4 AWG trigger as code-driven figures and confirm them against the edition the jurisdiction has actually adopted along with any local amendments, since the section numbering and details shift between cycles. The box itself has to be listed for the use, and the enclosure rating for the location follows the listing and the manufacturer's instructions. Where a project specification or the AHJ is stricter, that governs.

Units, terms, and conversions

Pull box sizing works in trade sizes and inches, with a few terms that carry the meaning.

Trade size is the nominal conduit designation, close to but not exactly the conductor-area dimension, and metric drawings give it as a metric designator. Box dimensions are inches in the NEC and millimeters in metric sources. Conductor size is AWG for smaller conductors and kcmil, thousands of circular mils, for larger ones, with the 4 AWG cutoff marking where 314.28 takes over from 314.16. The multipliers, 8 and 6, are pure ratios applied to the raceway trade size.

Pull box
Enclosure where conductors are pulled, routed, or spliced between raceways, sized by 314.28 geometry
Straight pull
Conductors enter one wall and exit the opposite wall in line, sized at 8x the largest raceway
Angle pull / U pull
Conductors change direction in the box, sized at 6x the largest raceway plus the others in the row
Trade size
Nominal raceway designation that the 8x and 6x multipliers are applied to
Box fill
The cubic-inch volume count for small device and outlet boxes under 314.16, a separate calculation
Conduit body
A fitting providing access at a bend or junction, with its own related sizing provisions

Related tools

Data centers send multiple parallel sets through large pull boxes, and PorchRocket's Ground Control selects commercial buildings by business type and size for contractors building that installation territory.

Next step: Search public feeder work

FAQ

How do you size a pull box?

Size a pull box from the conduit geometry under NEC 314.28, not the conductor count. For a straight pull, make the box length at least 8 times the largest raceway trade size. For an angle or U pull, use 6 times the largest plus the sum of the other raceways in the row. Take the worst case per direction.

What is the difference between box fill and pull box sizing?

Box fill, NEC 314.16, counts conductors, devices, and grounds in cubic inches to size small outlet boxes against crowding. Pull box sizing, NEC 314.28, works from conduit geometry so large conductors can pull and bend without damage. Box fill is volume; pull sizing is geometry. They apply to different boxes and are not interchangeable.

What is the 8 times rule for pull boxes?

The 8 times rule is the straight-pull requirement in NEC 314.28. The box length in the direction of the pull must be at least 8 times the trade size of the largest raceway entering it. A 3-in conduit straight through needs 8 times 3, or 24 in, of length. Verify the multiplier against the adopted code edition.

When do you need a pull box?

You need a pull box where a conduit run exceeds the bend limit, the equivalent of four quarter bends or 360 degrees total between pull points, or runs too long to pull in one pass. Past that, pulling tension climbs enough to damage the conductors. Crews also add pull points on long runs to make a hard pull manageable.

When does NEC 314.28 apply?

NEC 314.28 applies to pull boxes, junction boxes, and conduit bodies used with conductors 4 AWG and larger, regardless of system voltage. Below 4 AWG, the box is sized by box fill under 314.16. The conductor size is the trigger, so the same box can fall under either rule depending on what runs through it.

How do you size an angle pull box?

For an angle or U pull under NEC 314.28, the distance from the raceway entries to the opposite wall must be at least 6 times the largest raceway in the row plus the sum of the others. A row of 3-in, 2-in, and 2-in gives 6 times 3 plus 2 plus 2, or 22 in. Check entry-to-entry spacing too.

Does a junction box have to be accessible?

Yes. A junction box must stay accessible without removing part of the building or its finish, so you cannot bury it behind drywall, tile, or concrete. A box above a lift-out ceiling usually counts as accessible; one above a hard lid with no panel does not. Every box also needs a cover rated for the location.

What is the distance between raceway entries in a pull box?

Under NEC 314.28, the distance between two raceways enclosing the same conductors must be at least 6 times the trade size of the larger raceway, so the conductor does not bend too sharply between entry and exit. Two 3-in conduits carrying the same conductors need at least 18 in between them. Check this on every angle pull.

Can you use box fill to size a feeder pull box?

No. Box fill under NEC 314.16 sizes small boxes by cubic-inch volume and does not account for bending radius or pulling tension. For conductors 4 AWG and larger, use the 314.28 geometry, the 8 times straight-pull and 6 times angle-pull rules. Sizing a feeder box by fill leaves no room to pull or bend the conductors.

People also ask

Codes cited in this guide

This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.