CRAC / CRAH
On a computer room air conditioner (CRAC) or computer room air handler (CRAH) selection, identify net sensible duty and its test conditions before comparing unit counts. Trace the CRAC's refrigerant heat-rejection path or the CRAH's chilled-water dependency separately. Vertiv's centrifugal-fan CW106 schedule lists 99.4 kW sensible against 120.2 kW total at its stated conditions. The larger number cannot serve a 120.2 kW sensible room load; the fan configuration belongs with the rating.
Computer room air conditioner (DX) and computer room air handler (chilled water), the room units that often carry humidity control
Read the sensible-capacity row on the selection
Vertiv's Liebert CW brochure rates the CW106 with centrifugal fans at 99.4 kW net sensible capacity and 120.2 kW net total capacity with 75°F dry-bulb, 50% RH entering air, 45°F entering water, and a 10°F water-temperature rise. Its footnote identifies centrifugal-fan performance for this row even though the model also has an EC plug-fan option. Preserve the fan selection with the rating instead of applying the row to either configuration.
At those published conditions, two centrifugal-fan CW106 units provide 198.8 kW of sensible cooling. A 200 kW sensible load exceeds that pair's published duty, even though the total-capacity rows add to 240.4 kW. Three installed units with one unavailable leave the same 198.8 kW, so adding a third unit does not establish N+1 capacity for this 200 kW duty.
Entering-air temperature and humidity change coil performance. Preserve them with the water conditions, fan configuration, and capacity figures when comparing selections. The chilled-water versus DX guide explains the system choice; the selection sheet establishes what an individual unit removes at a stated duty.
Account for fan heat only once
Vertiv explicitly subtracts fan-motor heat from the Liebert CW capacity schedule to report net capacity. Deducting that heat again would understate the listed cooling. Conversely, using an unadjusted gross coil selection as room capacity overstates the heat the installed assembly can remove.
Keep fan power and room heat removal as separate entries in the commissioning record. A fan-speed change affects airflow, fan heat, and coil performance together. The comparison needs a new operating selection or measured duty; retaining an old capacity value beside a new fan setting loses the basis of the calculation.
Which rating standard belongs with CRAC and CRAH data?
AHRI's current publisher listing identifies AHRI 1360-2022 for inch-pound ratings and AHRI 1361-2022 for SI ratings of computer and data processing room air conditioners. AHRI excludes separately used components, such as individual condensing units or coils, from that standard's scope. A standalone coil rating therefore does not establish a complete room-cooling unit's rating.
Record the standard actually printed on each submitted schedule. The cited Liebert CW brochure labels its data to ASHRAE 127-2007; those legacy figures should retain that attribution when used to understand existing equipment. A current AHRI publication date does not retroactively relabel an older manufacturer's test basis.
Locate the upstream water pumps, control valves, and heat-rejection equipment on the layout from the white-space and gray-space guide. Two CRAHs sharing an unavailable water supply do not provide two independent cooling paths. For each standby test, record both remaining room-unit capacity and availability of the plant serving it.
Distinctions
- Total capacity
- The 20.8 kW gap between the cited CW106 total and sensible ratings represents latent moisture removal at those conditions. It cannot be added to the unit's sensible heat budget for servers.
- CDU
- Keep a coolant distribution unit's liquid-circuit duty outside the CRAH capacity total. Size the room air units for the heat remaining in the air after liquid cooling, using their net sensible selections at the specified room conditions.
Frequently asked questions
Is the model number the cooling capacity?
Use the performance schedule. The CW106 example has different total and sensible ratings, and both change with the entering conditions.
Does a spinning CRAH fan prove cooling is available?
No. Verify water temperature, water flow, valve response, and air-side heat removal. Air circulation can continue while the upstream chilled-water supply is unavailable.
Sources checked
Also defined as
- Datacenter: Computer room air conditioner and air handler, the perimeter cooling units
- Computer room air conditioner (DX) and computer room air handler (chilled water), the data-center forms of the two systems