Range

A cooling tower with 95°F inlet water and 85°F outlet water has a 10°F range; it still has a 10°F range at 101°F in and 91°F out. The second condition delivers much warmer water despite the identical difference. SPX explains this behavior at unchanged heat load and circulating flow. Diagnose range alongside outlet temperature, flow and wet-bulb approach rather than treating the temperature span as tower efficiency.

Hot water temperature entering the tower minus cold water temperature leaving it

Used across 2 Anvilfield field guides, most in HVAC.
Updated

The same range can accompany worse cold water

SPX Cooling's Thermal Science paper TR-017 explains that stopping tower fans at constant heat load and water flow degrades approach while leaving the stabilized range essentially unchanged. The loop moves to higher water temperatures until heat rejection again balances the process. Range alone therefore cannot serve as a tower-capacity acceptance measurement.

A 95°F inlet and 85°F outlet produce a 10°F range. If the loop stabilizes at 101°F in and 91°F out with the same heat input and flow, the range remains 10°F while the cold water supplied to the chiller is 6°F warmer. Record that 6°F increase as the change in water delivered to the chiller in the tower operating log; recording only range would hide it.

Use the process heat balance to interpret a changing span

SPX's Cooling Tower Performance paper works a duty of 1,000 gpm cooled from 100°F to 85°F as approximately 125,000 Btu/min, or 7.5 million Btu/h. For that published duty, 7.5 million Btu/h divided by 500 × 1,000 gpm gives the 15°F span. The conversion uses the water mass flow and specific heat, not a thermal efficiency percentage.

At the same 7.5 million Btu/h load, reducing flow from 1,000 to 750 gpm raises the calculated range from 15°F to 20°F using the same water-property approximation. A larger range can therefore reflect less water, rather than a better tower. Confirm measured flow when a temperature trend improves after a pump or valve change.

Keep inlet samples and basin mixing representative

SPX's performance paper notes that evaporation makes the water mass leaving the tower slightly smaller than the entering mass, and that a rigorous heat balance accounts for that difference. The familiar constant-flow shortcut is suitable for a quick water-side load calculation; a formal capability determination also needs the specified measurement and correction method.

Measure the hot-water temperature before distribution and the representative cold-water outlet after basin mixing. A reading beside makeup entry or in a stagnant basin corner need not represent the water delivered to the condenser. Record fan state, operating cells and entering wet-bulb temperature with the paired readings, then use the tower commissioning guide to compare the operating condition with the selected performance.

Distinctions

Approach
At 78°F entering-air wet bulb, the 85°F cold-water case has a 7°F approach and the 91°F case has a 13°F approach. Range remains 10°F in both cases, so approach reveals the performance change.
Instrument range
The pressure or temperature span an instrument can measure. That use of range describes the tool, not the cooling-water temperature difference.

Frequently asked questions

Is a higher cooling-tower range always better?

No. At unchanged load it can indicate reduced circulating flow. Read the cold-water temperature, approach and flow together.

Can fan failure leave a normal range?

Yes. At steady heat load and flow, both water temperatures can rise together while their difference stays about the same.

Sources checked

Also defined as

  • Hot water in minus cold water out, in degrees, set by load and flow
  • Hot water entering minus cold water leaving, set by load and flow

Where this shows up