ANVILFIELD Try FieldOS

HVAC

Cooling tower commissioning and water treatment field guide

Check tower thermal performance, establish the water-treatment controls and assign the inspection, monitoring and sampling duties in the water management program.

Cooling TowerWater TreatmentASHRAE 188LegionellaCommissioning

Direct answer

Cooling tower inspection and Legionella control combine component checks, water-treatment monitoring, representative sampling, corrective actions and a named owner for each duty. Set separate schedules under the site water management program, equipment instructions and applicable local rules. Commissioning also checks thermal performance against the specified test method and manufacturer curves.

On this pageThe cooling tower, and the two risks you commission againstOpen or closed-circuit: which tower is on the job?What are range and approach?How is the tower's thermal performance proven?The components: fill, drift eliminators, distribution, and basinWhat are cycles of concentration?Scale, corrosion, and the LSI balanceWhy do cooling towers grow Legionella?What is an ASHRAE 188 water management plan?What should a recurring cooling tower inspection cover?How do you verify and validate the Legionella program?Which inspection and sampling intervals apply in 2026?How should Legionella samples and corrective actions be handled?What do the inspection numbers actually tell you?Startup: cleaning, disinfection, and passivationCommissioning the controlsFreeze protection and winter operationDrift, plume, and placement away from air intakesThe condenser water loop and the chillerCooling towers in the data center cooling plantField checklistWhat to documentCommon mistakesFinding cooling tower commissioning and treatment accounts in your marketStandards and referencesUnits, terms, and conversionsMethodology

Key takeaways

  • Approach equals cold water out minus ambient wet-bulb and is the real performance number; a tower cannot cool below the wet-bulb.
  • CTI ATC-105 is the field acceptance test; a result at or above 100 percent of predicted capability passes, and test conditions must sit near design wet-bulb.
  • Cycles of concentration equals circulating conductivity divided by makeup conductivity; many systems run 2 to 6 cycles, set conductivity setpoint to makeup times target cycles.
  • Most cooling programs hold a slightly positive LSI, typically near 0 to plus 0.5; negative LSI is corrosive, positive is scaling.
  • ANSI/ASHRAE 188 requires the owner to run a written water management plan; CDC guidance points to locating the tower at least 25 feet from building air intakes.

The cooling tower, and the two risks you commission against

A cooling tower rejects heat by evaporating part of its circulating water into an air stream. The remaining water returns to the heat-rejection loop. Commissioning must check both thermal performance and the controls used to manage scale, corrosion and microbial growth. [1, 5]

Keep thermal acceptance and water management as separate deliverables. Record the tested operating conditions, chemical-control limits, monitoring responsibilities and unresolved defects. A satisfactory leaving-water temperature does not establish Legionella control.

Open or closed-circuit: which tower is on the job?

An open-circuit tower exposes the circulating process water directly to air. A closed-circuit fluid cooler keeps process fluid inside a coil and uses a separate external spray-water circuit during wet operation. Identify both circuits before assigning sampling, cleaning and treatment duties. [1]

A closed process loop does not remove the microbial risk in the external spray water. Both arrangements need the applicable water management controls. Compare cost, footprint and approach using the actual equipment selections; circuit type alone does not establish a fixed price or temperature penalty.

What are range and approach?

Range is the hot water in minus the cold water out. It is how many degrees the tower pulled off the water on one pass, and it is set by the heat load and the flow, not by the tower. A bigger load or a slower flow gives you a wider range. Range tells you how hard the building is working the loop.

Approach is cold water leaving minus entering-air wet-bulb temperature. It describes how closely the tower approaches its evaporative cooling limit. Compare approach at the specified flow, heat load and air conditions; a difference between operating points does not by itself diagnose fouling.

A conventional evaporative tower approaches the entering-air wet-bulb temperature from above. A smaller specified approach generally requires more heat-transfer capability for the same duty. Use the selected performance curve and the approved test conditions to assess the actual tower.

RangeRange = Thot water in − Tcold water out
ApproachApproach = Tcold water out − Tambient wet-bulb
Range
Hot water entering minus cold water leaving, set by load and flow
Approach
Cold water leaving minus ambient wet-bulb, the performance measure
Wet-bulb
The lowest temperature evaporative cooling can reach; the tower's floor

How is the tower's thermal performance proven?

CTI ATC-105 sets the field thermal acceptance-test method for water cooling towers. Measure entering and leaving water temperatures, circulating flow, entering-air wet-bulb and fan power, then evaluate capability using the agreed manufacturer curves and test method. The contract establishes acceptance and treatment of test uncertainty.

Confirm the permitted test-condition ranges and stability before scheduling. An off-design run is not automatically a valid acceptance test merely because someone corrected the temperatures. Record any test-party agreement on deviations and identify deferred acceptance work.

CTI STD-201 certification concerns the equipment rating; a project field test evaluates the installed tower under the agreed conditions. Record which proof the specification requires. A startup functional check, model certification and field thermal acceptance test are separate deliverables.

The components: fill, drift eliminators, distribution, and basin

The fill is where the heat transfer happens. It breaks the water into thin films or small droplets so the air has the most surface to work on. Film fill, the tight PVC honeycomb, gives the most surface in the least space and the best approach, but it plugs with debris, scale, and biofilm on dirty water. Splash fill, the staggered bars the water cascades over, is far harder to foul and is what you use on water that will not stay clean. The fill choice is a bet on how good the water treatment will be, and on a tower that gets neglected, film fill is the first thing to clog and steal the approach.

Drift consists of liquid droplets entrained in the exhaust air, separate from evaporated water. Those droplets can carry organisms from the circulating water. Inspect eliminator orientation, seating, gaps and damage against the installed model instructions. Drift performance is product-specific, and eliminators do not replace treatment or cleaning. [1, 5]

The distribution spreads water evenly over the fill, either pressurized spray nozzles in a counterflow tower or open gravity troughs in a crossflow tower. Uneven distribution starves part of the fill and kills the approach. The cold-water basin collects the cooled water and holds the makeup float valve, the suction, the bleed line, the strainer, and on most outdoor units the basin heater. The fan and drive pull the air, on a belt or gear drive or increasingly a direct-drive motor, often on a VFD so the controls can modulate airflow to hold a leaving-water setpoint.

What are cycles of concentration?

Cycles of concentration is the ratio of dissolved solids in the circulating water to the dissolved solids in the makeup water. Evaporation leaves the minerals behind. The water vapor that carries the heat away is nearly pure, so every gallon that evaporates concentrates the salts in the gallons that stay. Left alone, the tower would keep concentrating until it scaled solid. You hold it in check by bleeding off a fraction of the concentrated water, the blowdown, and replacing it with fresh makeup.

Cycles balance water consumption against the makeup-water chemistry and treatment limits. DOE describes many systems operating at two to four cycles, with higher cycles dependent on water quality and treatment. Anvilfield water-balance analysis finds that increasing from 3 to 6 cycles reduces makeup by 20% and blowdown by 60% at fixed evaporation with drift excluded. Set the operating target with the treatment specialist; the calculation is not a chemistry limit. [11]

In the field you do not measure dissolved solids directly, you measure conductivity, in microsiemens per centimeter, because conductivity tracks the dissolved salts closely and a probe reads it continuously. A conductivity controller watches the circulating water and opens the blowdown valve when conductivity climbs past the setpoint, then closes it when fresh makeup brings it back down. Set the setpoint as the makeup conductivity times your target cycles. Commissioning the conductivity controller, and proving the blowdown valve actually strokes, is one of the steps that quietly decides whether the tower scales in its first year.

Cycles of concentrationCycles = Conductivitycirculating / Conductivitymakeup
Cycles of concentration
Circulating dissolved solids divided by makeup dissolved solids
Blowdown / bleed
Concentrated water drained off to hold the cycles down
Makeup
Fresh water added to replace evaporation, drift, and blowdown

Scale, corrosion, and the LSI balance

Scale and corrosion are the two ways the chemistry goes wrong, and they pull in opposite directions. Scale is mineral dropping out of solution and plating onto hot surfaces, mostly calcium carbonate, and it insulates the condenser tubes and chokes the fill. Corrosion is the metal going into solution, eating the basin, the piping, and the tube walls. Water that is too scaling on one tower is too corrosive on the next, and the treatment program walks the line between them.

The Langelier saturation index (LSI) describes calcium-carbonate saturation using pH, calcium, alkalinity, temperature and dissolved solids. Negative values indicate undersaturation; positive values indicate supersaturation. It is not a direct corrosion-rate measurement, and neither sign guarantees corrosion or deposits. WHO explains this limitation in its discussion of corrosion indices. Set operating limits from the tower metallurgy, treatment program and measured condition rather than a universal LSI target. [12]

A real treatment program runs three chemistries together. A scale inhibitor, usually a phosphonate or polymer, holds the hardness in solution past where it would normally drop out. A corrosion inhibitor builds a protective film on the metal so the water does not eat it. A dispersant keeps suspended solids and the start of biofilm from settling and packing into the fill. These come as a blended product matched to the makeup water, the cycles, and the metallurgy. The water treatment vendor sets the program and the targets, and commissioning is where you confirm the feed equipment actually doses it and the test results land in the band the vendor specified.

Why do cooling towers grow Legionella?

Warm water, deposits, stagnation and biofilm support Legionella growth. A contaminated tower can spread organisms in liquid aerosols. Control those conditions through the water management program, effective treatment, cleaning, circulation and maintained drift eliminators. [1]

Have the treatment specialist select and monitor the biocide program for the equipment and water conditions. A chemical residual establishes a control reading, not proof that the whole system is free of Legionella. Follow product instructions, the site program and applicable requirements.

CDC recommends offline cleaning and disinfection at least annually. Local rules and the equipment instructions establish additional duties; the NYC schedule below requires cleaning at least twice per calendar year. Keep physical cleaning and chemical treatment assigned and documented. [1, 7]

What is an ASHRAE 188 water management plan?

ANSI/ASHRAE Standard 188, Legionellosis: Risk Management for Building Water Systems, is the standard that frames how a building controls Legionella, and the cooling tower is one of the systems it covers. It does not hand you a chemical recipe. It requires the owner to build and run a written water management plan, a WMP, specific to the building and its equipment, and to keep the records that prove the plan is being followed. In a growing number of jurisdictions, cooling-tower registration and a Legionella management plan are also a legal requirement, so confirm the local rule on top of the standard.

The plan is built around a set of elements. A program team that owns the decisions. A written description and a flow diagram of the water systems, so everyone is working from the same picture. An analysis of where Legionella can grow and spread, which identifies the control points. Control measures with defined limits at each point, the things you monitor and the numbers that mean in or out of control. Monitoring procedures that say what gets checked, how, and how often. Corrective actions for when a limit is exceeded. And verification and validation, plus the documentation that the program is doing what it is supposed to.

For a cooling tower, the control points are the ones you commission: the biocide residual, the conductivity and cycles, the pH and inhibitor levels, the bacterial and Legionella testing, and the condition of the drift eliminators and the basin. The plan sets the limit on each and the action when it is breached. The commissioning agent's job is to hand the owner a tower that is set up to run inside the WMP and the documentation that proves where it started. The plan itself is the owner's to run for the life of the tower, and the standard is explicit that it is an ongoing program, not a one-time startup check.

What should a recurring cooling tower inspection cover?

Start with the equipment tag, operating mode, inspected cell, water-system identifier, date, inspector and accessible areas. Two cells can share one treatment circuit. Record cells and circuits separately so a good reading from the operating basin does not conceal an isolated, stagnant compartment. CDC identifies stagnation, deposits and drift control as program concerns. [1]

Use the installed model's manual to set component tasks. EVAPCO's July 2026 cooling-tower manual gives monthly checks for spray distribution and bleed-valve operation, with quarterly drift-eliminator checks. Those are manufacturer recommendations for its equipment, distinct from a jurisdiction's compliance inspection. Increase attention when findings or the site program require it. [5]

The worksheet below organizes observations; it does not authorize reaching past guards or entering a basin. Arrange safe access and the approved equipment isolation before opening or servicing components. Record an inaccessible item and assign a return visit instead of marking it satisfactory.

Inspection areaRecord the observationAssign the follow-up
Basin, strainers and fillDeposits, debris, fouling and blocked passages; tag photographs.Cleaning assessment and access limits.
Drift eliminatorsMissing panels, gaps, damage and seating.Repair scope and reinspection evidence.
Distribution and idle cellsUneven wetting, blocked nozzles and stagnant sections.Operator review of circulation and treatment coverage.
Feed, bleed and sensorsAlarms, chemical availability and independent readings.Treatment specialist's control review.
Fan, drive and structureVisible damage, leaks and vibration complaints.Qualified mechanical assessment and isolation plan.

How do you verify and validate the Legionella program?

Verification checks whether people performed the written program. Validation evaluates whether it controls the hazardous conditions. CDC separates these duties and identifies environmental Legionella testing as one validation option. A completed cleaning ticket establishes a task record; evaluate its effectiveness using the program's inspection findings, operating trends and testing plan. [2]

Build a responsibility register with the owner, operator, treatment provider, cleaner, sampler, laboratory and after-hours decision maker. Each control point needs its monitoring method, site-approved limits, frequency, response and escalation contact. Close an exception with the action, completion time, follow-up result and reviewing person's name. A monthly contractor visit leaves the assigned between-visit duties with the operator. [2]

  • Match the current flow diagram to operating and standby cells.
  • Identify the person checking each limit between contractor visits.
  • Reconcile missing readings, overdue tasks and unresolved alarms.
  • Confirm sampling locations, reporting units and result recipients.
  • Record corrective actions and the evidence used to close them.
  • Review the program after equipment, operating-mode or responsibility changes.

Which inspection and sampling intervals apply in 2026?

Keep the schedules on separate calendar lines. CDC recommends offline cleaning and disinfection at least annually, with maintenance frequency dependent on design, load and local conditions. That recommendation does not establish a nationwide legal interval. Apply the address-specific rule and equipment instructions when setting the program. [1]

New York City illustrates why an old quarterly sampling allowance needs review. Starting May 8, 2026, NYC requires Legionella sampling no more than 31 days apart and upload of collection dates within five days. Its current operating guidance keeps qualified-person compliance inspections at least every 90 days. [6, 7]

TaskNYC operating-system requirementKeep in the record
Compliance inspectionAt least every 90 days by the Qualified Person.Findings, deficiencies and corrective actions.
Legionella cultureWithin 3 to 14 days after startup; thereafter no more than 31 days apart.Collection date, laboratory report and response.
Routine water chemistryAt least three times weekly; no more than two consecutive days between measurements.pH, temperature, conductivity and disinfectant residual.
CleaningAt least twice per calendar year, including before seasonal startup; more when required.Cleaning scope and treatment coordination.

NYC requirements only, reviewed November 5, 2026. Sources [6] and [7] also cover summertime hyperhalogenation and additional testing. Build the complete site calendar from the current rules.

How should Legionella samples and corrective actions be handled?

Agree on the sampling plan before collecting bottles: representative locations, operating conditions, laboratory method, handling requirements and who receives results. Follow the laboratory's collection instructions and preserve the chain of custody. Record recent cleaning or disinfection so the program team can interpret the sample in context. CDC emphasizes a plan representing the system and a defined purpose for testing. [3]

Keep culture results and molecular results in their reported units. Culture commonly reports colony-forming units, or CFU; molecular testing may report genomic units and may detect DNA from dead organisms. Those results are not directly interchangeable. A nondetect is limited by the method, sample locations and detection limit; it does not certify that the tower is free of Legionella. [3]

Use the site's written corrective-action criteria and applicable local requirements to assign treatment review, cleaning, disinfection, resampling, notifications and return-to-service authority. Avoid adopting a universal concentration threshold from another jurisdiction. Testing during a disease investigation must be coordinated with the authority having jurisdiction. Keep that response scope separate from routine service. [3, 7]

What do the inspection numbers actually tell you?

Anvilfield analysis gives 4.0 cycles for circulating conductivity of 1,920 microsiemens per centimeter and makeup conductivity of 480: 1,920 / 480 = 4.0. Conductivity is an operating approximation of concentration; microbial control is assessed separately.

A controller display of 2,400 differs from the independent 1,920 reading by 480, or 25% of the independent reading. Confirm sampling conditions, instrument calibration and probe condition before changing the treatment target.

For NYC routine sampling on November 5, 2026, the 31-day maximum interval puts the next latest routine collection on December 6. Schedule earlier for access and laboratory logistics; startup or corrective-action sampling has its own deadlines. [6, 7]

Startup: cleaning, disinfection, and passivation

Before startup, inspect and clean construction debris from the tower and connected piping. Coordinate cleaning and disinfection with the treatment specialist, manufacturer instructions and the water management program. Record the completed work before normal operation begins. [1, 5]

New galvanized surfaces require manufacturer-directed passivation. EVAPCO specifies pH 7.0 to 8.0 during passivation for the galvanized equipment in its cited manual. Have the treatment specialist establish the compatible chemistry, monitoring and completion criteria for the installed unit. Do not substitute an acidic startup recipe or a fixed duration from another model. [5]

The initial chemical feed has to be live before the tower runs at load. Inhibitors and biocide dosed, the conductivity controller bleeding to target cycles, and the first water sample pulled and logged as the baseline. That baseline is the number every later test gets measured against, so it belongs in the commissioning record, not in someone's memory.

Commissioning the controls

The controls are where the thermal side and the water side meet, and each loop gets functionally tested and recorded. The fan control modulates airflow to hold the leaving condenser-water temperature, usually a VFD ramping the fan or staging cells on a multi-cell tower. Confirm it actually holds the setpoint and that the staging and the VFD do not fight each other or short-cycle. On many plants the setpoint resets against the wet-bulb or the approach, so the tower makes the coldest water it can without overspending fan energy. Prove the reset moves the setpoint the right direction.

The water-side controls each get a functional test. The makeup float or valve holds the basin level and does not overflow or run the basin dry. The conductivity controller reads correctly and strokes the blowdown valve at the setpoint, which you verify by watching conductivity drop when it opens, not by trusting the display. The chemical feed pumps for inhibitor and biocide dose on their timers or their water-meter signal, and the approved dosing controls are programmed. The basin heater energizes on its thermostat and is interlocked so it cannot fire on a dry basin.

Then prove the alarms, because an alarm nobody tested is an alarm that will not save the tower. Low basin level, low or high conductivity, chemical drum low or empty, vibration on the fan, and basin-heater fault should each annunciate where someone will see it. The alarm that matters most over the tower's life is the one that says the water treatment has stopped working, the empty chemical drum or the failed feed pump, because a tower running with no biocide is the failure that grows into a Legionella problem quietly.

Freeze protection and winter operation

Protect idle basin water and exposed piping for the site winter conditions. EVAPCO describes basin heaters designed to maintain 40°F basin water at their specified design ambient temperature while circulation is stopped. Verify the actual heater capacity, control setpoint, low-water protection and operating interlock for the installed equipment. [5]

During cold-weather operation, inspect for icing and use the installed model's approved airflow, bypass and operating controls. Fan reversal and bypass arrangements are equipment-specific. Verify the permitted sequence before commanding a de-ice cycle. [5]

The cleaner answer where the design allows it is to move the water indoors. A remote or indoor sump keeps the working volume in a heated space, so the basin outdoors drains down when the tower is off and there is nothing outside to freeze. Whichever approach the design used, commission it: prove the basin heater and its cutoff, the bypass, and the de-ice logic actually function before the first hard freeze, not during it.

Drift, plume, and placement away from air intakes

Visible plume is condensed water vapor; drift is liquid water carried out of the tower. Drift can transport contaminants from the circulating water. A visible plume does not establish whether hazardous drift is present. Maintain the specified eliminators and treatment controls, and assess placement against air intakes. [1]

The placement rule that matters is keeping the tower discharge away from anything that breathes air into the building. CDC guidance points to locating a tower at least 25 feet from building air intakes so the drift plume is not pulled into the ventilation system, and to account for prevailing wind, which can push the effective distance well past that. A tower set close to a fresh-air intake, or upwind of an operable window or a public space, turns every gap in the water treatment into an exposure path straight into the building.

On commissioning, you cannot move a tower, but you can document the as-built relationship to intakes and operable openings and raise it if it is short. You also confirm the drift eliminators are fully installed and undamaged after any fill or basin work, because that is the controllable half of the drift risk and it is the half that gets left out after maintenance.

The condenser water loop and the chiller

The tower does not work alone. It is the heat-rejection end of the condenser-water loop, and the chiller is the other end. The chiller pulls heat out of the building's chilled water and dumps it, plus the compressor's own work, into the condenser water. The condenser pump pushes that warm water out to the tower, the tower rejects it to the air, and the cooled water comes back to the condenser. Commissioning the tower means commissioning it as part of that loop, not as a box on a roof.

Match condenser-water flow to the chiller and tower selections. Compare range and approach at the recorded load and wet-bulb conditions, then investigate differences through flow measurements, sensor checks and component inspection. A wide approach alone does not identify the failed component.

Watch the condenser approach on the chiller too, the gap between the leaving condenser water and the refrigerant condensing temperature. When that approach widens over time at steady conditions, the condenser tubes are scaling or fouling, which is the water treatment talking through the chiller. The tower and the chiller share one water problem.

Cooling towers in the data center cooling plant

Cooling architecture affects both electricity and water consumption. Evaporative operation uses water through evaporation and blowdown; dry operation rejects heat without evaporating tower water. Hybrid equipment combines modes according to its design and controls. [11]

Compare actual operating profiles for the site climate and load. Dry-mode hours and annual water savings require project data. A hybrid system with a wet circuit retains the associated treatment and Legionella-control duties. [1, 5]

Field checklist

0 of 11 complete

Want this checklist to run itself on every job — with photo proof and a signed record crews can hand the customer? That's FieldOS.

What to document

The commissioning record is what the owner runs the water management plan against, and what a public-health investigator asks for if a culture ever comes back hot. Capture the tower as-built and the conditions it was proven at, the water-side baseline, and the control setpoints, so the day-one numbers are on paper and not in a memory that left with the startup tech.

Record the tower make, model, type, and whether it is CTI certified. Record the test conditions and results: range, approach, flow, ambient wet-bulb, fan power, and the percent of predicted capability. Record the water baseline: cycles, conductivity setpoint, pH, inhibitor and biocide levels, and microbial results required by the site sampling plan. Record that the water management plan exists, who owns it, and that the commissioned limits match it. The tower the building gets is only as good as the record that proves where it started.

Field to recordWhy it matters
Tower type and model, CTI certifiedSets which proof and which curve apply
Range at testConfirms the load and flow seen by the tower
Approach vs design at actual wet-bulbThe real performance number, corrected to conditions
Ambient wet-bulb at testThe floor the tower is judged against; validates the test
Circulating flow and delta-TTies the tower to the chiller and condenser loop
Cycles of concentration and conductivity setpointThe scale-versus-water-waste balance, baselined
Biocide residual and required microbial baselineThe day-one biological condition for the WMP
Water management plan owner and control limitsProves the ASHRAE 188 program is in place

Common mistakes

  • Handing over a tower with no written water management plan, so the Legionella controls have no owner and no limits.
  • Leaving drift eliminators cracked, sagging, or out after a fill cleaning, which bypasses the last barrier against contaminated aerosol.
  • Running cycles of concentration too low, wasting water and chemical, or too high, scaling the fill and condenser tubes and turning the water corrosive.
  • Skipping the pre-startup cleaning and disinfection, so the first biofilm seeds before treatment ever starts.
  • Running a new galvanized tower hard and alkaline before passivation, growing white rust and wrecking the corrosion protection.
  • Accepting a thermal result at an off-design wet-bulb without correcting to the curve, so the tower looks fine and is not.
  • Commissioning a tower set too close to a fresh-air intake or upwind of occupied space and not flagging the placement.
  • Leaving the basin heater, low-water cutoff, or bypass uncommissioned and discovering it during the first hard freeze.

Finding cooling tower commissioning and treatment accounts in your market

The strongest commissioning prospect has a real startup date, a defined tower system, and an owner who will carry the program after turnover. Look for new or replacement towers, plants returning from extended shutdown, and facilities preparing a treatment contract. An example target is a hotel with two cells on one condenser-water system, a named facilities manager, and an agreed startup window. Record installation age, replacement dates, cell count, system volume from the design, and which equipment is actually changing.

Qualify the operating handoff before quoting chemicals or labor. Ask for the water management program, makeup-water information, treatment history, controller and meter inventory, and the person responsible for each control action. Confirm roof access, isolation, drain and discharge arrangements, sampling points, and who can provide load for the performance check. CDC cooling tower guidance calls for manufacturer-directed cleaning and disinfection around commissioning and startup, and for a water management program. Translate the applicable requirements into this plant’s written scope and responsibilities.

Find candidate projects through mechanical and replacement permits, planning and capital project records, public commissioning or water-treatment bids, and tower registries where available. Use imagery to locate likely equipment and compare site layouts. New York City’s inspection records illustrate why a public record needs checking: historical entries can include inactive towers. Verify the current system and procurement status with the operator. A permit for a new tower gives you a project to research, not proof that a treatment provider has yet to be selected. For a tower search defined around that commissioning territory, PorchRocket's Asset Search accepts custom criteria for assets visible from above.

Separate the startup sale from the recurring account. For a typical two-cell plant, use $6,000 for the agreed startup cleaning, treatment setup, baseline measurements, controls checks, and handoff documentation. The case uses another $750 per month for a defined treatment service and reporting scope, or $9,000 over twelve months. Anvilfield research puts first-year revenue at $15,000. Direct labor, chemicals, testing allowances, travel and equipment total $10,500, leaving $4,500 gross profit. Allocate $2,250 of overhead and the remainder is $2,250 before income tax. A subsequent year starts from the $9,000 service input, subject to renewal and changed conditions.

Set monitoring and microbial-testing frequencies separately from the monthly commercial visits. Set the actual schedule from the site program, manufacturer, and applicable requirements, with the owner’s between-visit duties written down. Identify laboratory allowances, corrective response, chemical usage limits, and mechanical repairs separately. Keep commissioning acceptance tied to the specified test conditions and records. The account becomes repeatable when the operator knows who checks each parameter, who acts when it moves, and what the recurring fee actually buys.

Standards and references

ANSI/ASHRAE Standard 188, Legionellosis: Risk Management for Building Water Systems, is the central standard for the water side. It requires the owner to develop and maintain a written water management plan for building water systems including cooling towers, built around a program team, system description and flow diagram, hazard analysis and control points, control limits, monitoring, corrective action, and documentation. Confirm the current edition, since the standard is revised and the program requirements are updated.

On the thermal side, the Cooling Technology Institute, CTI, owns the performance documents. CTI ATC-105 is the field acceptance test code for water cooling towers, and CTI STD-201 is the thermal performance certification program for the equipment. ASHRAE Standard 90.1 sets minimum efficiency for heat-rejection equipment, which the tower selection has to meet. Use the standard that governs the point, and let the project specification override a rule of thumb when it is stricter.

Public-health and regulatory guidance backs the standard. CDC publishes cooling-tower-specific Legionella control guidance, including pre-commissioning disinfection, cleaning frequency, drift-eliminator use, and the 25-foot separation from air intakes. OSHA addresses Legionella as a workplace hazard, including cleaning and disinfection frequency. A growing number of state and local jurisdictions now require cooling-tower registration and a Legionella management plan, so confirm the local rule on top of the standard. The water-treatment vendor sets the chemical program and the test limits for the specific makeup water and metallurgy, and the project specification and equipment submittals control the numbers.

For this inspection extension, the November 5, 2026 reference basis is ANSI/ASHRAE Standard 188-2021 and ASHRAE Guideline 12-2023. Check applicable addenda and the edition incorporated into the local rule or contract. Standard 188 does not itself establish a nationwide registration law. For electrical repairs, use NEC 2026 where adopted; otherwise this guide uses a NEC 2023 reference basis, subject to local adoption and amendments. [4, 8, 9]

EVAPCO's July 2026 manual specifies galvanized-steel passivation pH of 7.0 to 8.0. Use the installed equipment instructions and treatment program for startup and operating limits. [5]

Units, terms, and conversions

Cooling-tower work mixes thermal terms with water-chemistry terms, and the same quantities show up in different units across a manufacturer sheet, a balancing report, and a water-treatment log.

Temperatures and the wet-bulb run in degrees F on most US drawings and degrees C on metric and many manufacturer documents. Flow is gallons per minute, often tied to tons of cooling at the condenser. Conductivity, the field stand-in for dissolved solids, is microsiemens per centimeter, and dissolved solids themselves are parts per million. LSI is dimensionless and describes calcium-carbonate saturation, not a measured corrosion rate. Drift is a percentage of circulating flow. Cycles of concentration is a ratio, dimensionless. Keep each in the unit the document that controls it uses, and convert deliberately rather than eyeballing it.

Range
Hot water in minus cold water out, in degrees, set by load and flow
Approach
Cold water out minus ambient wet-bulb; the tower's performance measure
Wet-bulb
Lowest temperature evaporative cooling can reach; the tower is rated against it
Cycles of concentration
Ratio of circulating to makeup dissolved solids, held with blowdown
Blowdown / bleed
Concentrated water drained off to control cycles and scaling
LSI
Langelier saturation index; negative indicates calcium-carbonate undersaturation and positive indicates supersaturation
Drift
Liquid droplets carried out in the air stream, the Legionella aerosol path
ASHRAE 188
The standard requiring a written water management plan for Legionella risk

Methodology

Anvilfield research combines the cited agency and manufacturer guidance with reproducible water-balance, scheduling and account calculations. The conductivity case uses stable makeup chemistry and comparable temperature-compensated readings. With fixed evaporation E and negligible drift, blowdown B = E/(C - 1) and makeup M = E + B; changing C from 3 to 6 gives 20% less makeup and 60% less blowdown.

The account model uses a two-cell plant, $6,000 startup revenue, twelve monthly fees of $750, $10,500 direct cost and $2,250 overhead. These are research-model inputs, not surveyed contractor prices or an inspected customer account. Technical limits retain their source and jurisdiction; the service fee does not determine monitoring or sampling frequency.

Related tools

Next step: Request a cooling tower search

FAQ

What are range and approach on a cooling tower?

Range is the hot water entering minus the cold water leaving, set by the load and the flow. Approach is the cold water leaving minus the ambient wet-bulb, and it is the performance measure. A smaller approach means the tower cools closer to the physical limit, since a tower cannot cool below the wet-bulb.

What is an ASHRAE 188 water management plan?

ASHRAE Standard 188 requires building owners to keep a written water management plan controlling Legionella risk in systems like cooling towers. It sets a program team, a flow diagram, hazard analysis and control points, monitoring with limits, corrective actions, and documentation. Confirm the current edition and any local cooling-tower registration rule.

What are cycles of concentration in a cooling tower?

Cycles of concentration compare dissolved solids in circulating water with makeup water. Temperature-compensated conductivity is a practical operating proxy. Set cycles from makeup-water chemistry, metallurgy and the treatment program; monitor blowdown and control readings.

Why do cooling towers grow Legionella?

A tower holds warm water with nutrients and huge wetted surface area for biofilm, which is ideal for Legionella, and it then makes aerosol and throws it into the air. That creates an exposure route when the system is contaminated. Control needs biocide, cleaning, drift eliminators, and a water management plan, not chemistry alone.

What is the difference between an open and a closed-circuit cooling tower?

An open tower exposes process water directly to air. A closed-circuit fluid cooler keeps process fluid in a coil and uses a separate spray-water circuit in wet operation. That spray circuit still needs water management and Legionella controls. Compare equipment selections for cost and performance.

How is a cooling tower's thermal performance tested?

You compare the tower to its design curve using CTI ATC-105, measuring hot and cold water temperatures, flow, ambient wet-bulb, and fan power, then computing capability as a percent of predicted. CTI STD-201 certifies the model's rating. Test conditions must sit near design wet-bulb, or the result is corrected to the curve.

What is the LSI in cooling tower water treatment?

LSI is an index of calcium-carbonate saturation. Negative values indicate undersaturation and positive values indicate supersaturation. It does not measure corrosion rate or establish a universal treatment target. Evaluate corrosion and deposits through the equipment-specific treatment program.

How far should a cooling tower be from air intakes?

CDC guidance points to at least 25 feet between a cooling tower discharge and building air intakes, so the drift plume is not pulled into the ventilation system, and to account for prevailing wind that can push the needed distance further. Placement is set at design, so flag a short distance rather than accept it.

What do I do before starting up a new galvanized cooling tower?

Clean and disinfect under the manufacturer instructions and water management program, then document passivation. The cited EVAPCO manual specifies pH 7.0 to 8.0 during galvanized-steel passivation. Use the installed model's chemistry and completion criteria.

How does a conductivity controller manage cooling tower blowdown?

A conductivity probe reads the circulating water continuously, in microsiemens per centimeter, as a stand-in for dissolved solids. The controller opens the blowdown valve when conductivity passes the setpoint and closes it as fresh makeup dilutes it. Set the setpoint to makeup conductivity times your target cycles, and verify the valve actually strokes.

How do I price tower startup separately from ongoing treatment?

Define the one-time cleaning, treatment setup, controls checks, baseline testing, and handoff package first. Price recurring service from the actual program, operating conditions, chemical use, testing, and reporting duties. Contractor visit frequency does not replace the owner’s monitoring responsibilities or the site’s required testing schedule.

People also ask

Codes cited in this guide

This guide is written and reviewed against the published standards below. Always confirm the current adopted edition with the authority having jurisdiction.

Sources checked