Field glossary · measurement
Residual rate
Residual rate is the binder quantity that remains on each unit of pavement area after emulsion water leaves. A target of 0.06 gallon per square yard needs 0.10 gallon per square yard of emulsion containing 60 percent binder by volume. Equal-volume water dilution raises that spray requirement to 0.20 while leaving the target unchanged. FHWA's volume method uses quantities corrected to 60°F; mass-certified residue also requires a density conversion.
The amount of actual asphalt left after the water or solvent leaves, the number specifications set for tack
Convert the required binder film into distributor gallons
FHWA-HIF-16-017 describes undiluted tack emulsions as typically containing 57 to 70 percent residual asphalt and requires volume calculations to be corrected to 60°F. Write the target residual, original emulsion residue, added-water ratio and volume reference temperature at the top of the shot calculation. A hot distributor reading and a reference-temperature volume are different quantities.
Using volumes corrected to 60°F and 60 percent asphalt by volume, a target of 0.06 gallon per square yard residual requires 0.10 gallon per square yard of undiluted emulsion: 0.06 divided by 0.60. Diluting that emulsion with an equal volume of water makes its binder concentration 30 percent and requires 0.20 gallon per square yard of diluted liquid. Both applications deliver 0.06 gallon per square yard residual.
A 10,000-square-yard shot has three different quantities
For 10,000 square yards, those rates require the quantities below, all on the same 60°F volume basis. The additional water changes the distributor load and drying burden without increasing the binder left on the pavement.
Caltrans' April 2024 Tack Coat Guidelines permit dilution up to one part water to one part emulsion for suitable slow- or quick-setting grades, with the supplier performing the dilution. That instruction does not permit adding water to every emulsion grade. See the emulsion entry for the designation and delivered blend.
| Quantity for 10,000 square yards | Undiluted shot | 1:1 diluted shot |
|---|---|---|
| Original emulsion | 1,000 gal | 1,000 gal |
| Added dilution water | 0 gal | 1,000 gal |
| Total liquid sprayed | 1,000 gal | 2,000 gal |
| Residual binder | 600 gal | 600 gal |
Verify rate and distribution separately
Caltrans' 2024 guidelines identify California Test 339 for determining distributor spread rate by collecting and weighing the application. For a mass-certified residue, residual volume per area equals emulsion volume per area multiplied by emulsion density, residue mass fraction and the reciprocal of binder density, with consistent temperature and density units. Do not enter a mass percentage directly into the volume-fraction example above.
FHWA-HIF-16-017 recommends distributor calibration at least annually and periodic trial applications to verify nozzle operation. A tank drawdown divided by total area establishes an average; local collection measurements and the spray pattern establish whether that average is distributed evenly. Carry those checks into the tack-coat guide with the load certification.
Distinctions
- Sealcoat spread rate
- A mixed sealer contains water, sand and other ingredients. Its gallons-per-area specification is not automatically an asphalt residual requirement.
Frequently asked questions
Can a higher spray rate still leave too little asphalt?
Yes. Added dilution raises liquid volume while lowering binder concentration. Calculate the residual from both figures rather than comparing spray gallons alone.
Sources checked
Also defined as
- The asphalt left on the surface after the emulsion breaks, in gal/sy; the number the spec controls