Triplen harmonics
Triplen harmonics belong to orders divisible by three. In half-wave-symmetric load waveforms, the even orders disappear, leaving the familiar third, ninth and fifteenth. Corresponding balanced three-phase components reinforce in the neutral: 20 A of third harmonic per phase produces 60 A at that frequency. Combine different harmonic frequencies by root-sum-square, not simple addition, when calculating the neutral's total RMS current.
Odd multiples of the third harmonic that add on the neutral of a three-phase MWBC
Why 120 degrees becomes a full turn
Schneider Electric's Electrical Installation Guide identifies the triplen family by harmonic orders that are multiples of three. Fluke's service-panel note focuses on the usual odd triplen currents from nonlinear single-phase loads. Baylor's power-system harmonics notes show why half-wave symmetry removes even orders, including the sixth and twelfth; the commonly discussed neutral-loading orders are therefore 3, 9 and 15.
Harmonic phase displacement is harmonic order times the fundamental displacement. With three similar phase waveforms separated by 120 degrees, the third harmonic shifts by 360 degrees and the ninth by 1,080 degrees, both whole turns. At 60 Hz they occupy 180 Hz and 540 Hz; at 50 Hz the corresponding frequencies are 150 Hz and 450 Hz.
One neutral calculation, two different kinds of addition
Schneider Electric's Electrical Installation Guide expresses total RMS current as the square root of the sum of the squared RMS harmonic components. Components at different frequencies therefore do not add arithmetically, even when each harmonic order adds across the three phases.
Take three identical line-to-neutral loads, each drawing 40 A fundamental, 20 A third harmonic and 5 A ninth harmonic, with no other components. Each phase carries sqrt(40² + 20² + 5²) = 45 A RMS. The balanced fundamentals cancel in the neutral. Its third harmonic is 3 x 20 = 60 A and its ninth harmonic is 3 x 5 = 15 A.
The resulting neutral current is sqrt(60² + 15²) = 61.8 A RMS, not 75 A. It exceeds the 45 A phase current despite perfect fundamental balance. This calculation assumes identical waveforms and their normal phase displacement; measured phase differences and unequal loads require the corresponding per-order vector sums.
Read the spectrum before blaming phase imbalance
Schneider's guide specifically connects increased neutral current with triplen harmonics in three-phase, four-wire systems. A 60 Hz neutral component and a 180 Hz neutral component point to different causes: fundamental imbalance and third-harmonic addition. A single total-RMS reading does not separate them.
Record the phase and neutral spectra during the same load condition. The PDU and RPP commissioning guide provides the operating context for that record. The shared-neutral guide addresses circuit arrangements; the harmonic calculation explains why equal phase totals alone do not prove a lightly loaded neutral.
Distinctions
- Harmonic order versus THD
- Order identifies a particular frequency component. Total harmonic distortion combines harmonic content into one ratio, so equal THD values do not establish equal triplen content or equal neutral current.
Frequently asked questions
Why is the neutral current 61.8 A rather than 75 A in this example?
The 60 A third-harmonic current and 15 A ninth-harmonic current occupy different frequencies. Schneider's RMS relationship combines their squared amplitudes, giving sqrt(60² + 15²), while arithmetic addition applies to the aligned phase contributions within each order.
Sources checked
- Fluke: Power quality troubleshooting at the service panel, harmonics discussion
- Schneider Electric: Electrical Installation Guide 2018, harmonic management and neutral-current sections
- Schneider Electric: Electrical Installation Guide, RMS formula and harmonic components, online version checked November 5, 2026
- Baylor University: Understanding Power System Harmonics, April 2012, waveform symmetry and Fourier-series notes
Also defined as
- Datacenter: The 3rd, 9th, 15th and higher harmonics that add on the neutral instead of cancelling