ANVILFIELD Try FieldOS

Field glossary

Terms — 0-9 & symbols

66 field terms starting with 0-9 & symbols, 8 with a full reference page. Each links to the Anvilfield guides where the term is used on the job.

#15 / #30 felt
Asphalt-saturated felt by an old weight-per-square convention, #30 being the heavier, tougher rollIn: Roofing underlayment types
$/MW / $/kW
Cost per megawatt or kilowatt of IT capacity, the common way data center capital cost is benchmarkedIn: Data center buildout phases
% Gmm
In-place density as a percentage of Gmm; 100 percent minus % Gmm is roughly the air-void contentIn: Asphalt compaction window
% Gmm / air voids
In-place density as a percentage of the theoretical maximum specific gravity; the remainder is roughly the air-void contentIn: Cold-weather asphalt pavingAsphalt compaction window
%Z
Transformer percent impedance from the nameplate, the percent of rated voltage that drives full-load current into a shorted secondaryIn: Available fault current studyOne-line diagram field guide
%Z (percent impedance)
Winding impedance as a percent of rated values; sets the downstream available fault currentIn: Padmount transformer energization
α
Fiber attenuation in dB per km, higher at shorter wavelengths, from the fiber data sheetIn: Fiber splice loss budget
ρ (rho)
Soil resistivity, in ohm-meters or ohm-centimetersIn: Ground resistance testing
-850 mV criterion / reference electrode
A polarized potential of -850 mV or more negative versus a copper/copper-sulfate electrode, the standard proof of protection in soilIn: Cathodic protection field guide
0-10V
Analog dimming over a low-voltage control pair, 10 V full to about 1 percent floor, polarity-sensitiveIn: Lighting controls and dimming
0-10V dimming
Low-voltage control pair that tells the LED driver how to dim, separate from the line voltageIn: LED lighting retrofit
0.083 h
Five minutes expressed in hours, the standard non-voice alarm duration; use 0.25 h for 15 min voiceIn: Fire alarm install and test
0U / vertical
A strip mounted in the rear channel that takes no rack-unit space from the 19 in fieldIn: Data center rack PDU types
0U PDU
Vertical rack power strip mounted in the side channel, taking no rack-unit spaceIn: Data center rack cable managementData center cabinet and rack types
1.25
Aging and derating margin applied to the summed ampere-hoursIn: Fire alarm install and test
1/0 AWG
The minimum conductor size the NEC permits to be paralleled for power, with narrow exceptionsIn: Parallel conductors, NEC
100 percent tie-off
Staying connected to an anchor at all times at height, including during transitions, the core of fall protectionIn: Cell tower and antenna install
11-month inspection
A full warranty walk before the one-year warranty expires, to catch defects while the contractor still owes the fixIn: Closeout and warranty management
13-week cash forecast
A rolling week-by-week projection of cash in against cash out for the next quarterIn: Cash flow and forecasting field guide
150 percent point
At 150 percent of rated flow the pump must produce at least 65 percent of its rated pressureIn: Fire pump and standpipe guideFire pump acceptance test
19 in rack
The 482.6 mm rail-to-rail mounting width standardized in EIA-310 and IEC 60297In: Data center cabinet and rack typesRack readiness field guide
1:150 / 1:300 ratio
Square feet of attic floor per square foot of net free vent area required by codeIn: Roof attic ventilation
1:48 slope
About 2 percent, the maximum slope in all directions for accessible spaces and aislesIn: ADA accessible parking layout
2 AWG
The minimum bare copper conductor size for a ground ring, with heavier sizes common by designIn: Ground ring electrode field guide
2-pipe / 4-pipe
One coil on a seasonal changeover loop, versus separate heating and cooling coils available at onceIn: Fan coil unit field guide
2/10 net 30
A supplier term: 2 percent off for paying in 10 days, or the full amount due at 30In: Cash flow and forecasting field guideAccounts payable and supplier management
24/7 CFE
Carbon-free energy matched to consumption every hour, not averaged annuallyIn: Data center sustainability reporting
25 percent of LEL
The 1 percent hydrogen by volume ceiling the codes commonly hold the room belowIn: Battery room ventilation and hydrogen safety
25 percent rule
The trigger to pump when grease plus solids reach 25 percent of the liquid depthIn: Grease interceptor field guide
25 sync-check
ANSI device 25, the permissive relay that only allows a close when sync conditions are metIn: Generator paralleling switchgear
27
Cubic feet in one cubic yard, the divisor that takes the volume to orderable unitsIn: Concrete estimating and takeoff
2N / N+1
Redundancy levels on the critical power and cooling path, full duplicate versus one spare unitIn: AI GPU rack readiness
2N / system-plus-system / dual-bus
Two complete independent systems, each a full N, kept apartIn: UPS topology and redundancy design
3-2-1 rule
Three copies, two media, one offsite; extended to 3-2-1-1-0 with an immutable copy and tested restoresIn: Data center disaster recovery
3-pole / 4-pole
Solid neutral switched through, or neutral switched with the phases, which sets the generator groundingIn: Standby generator installATS commissioning field guide
3-pole vs 4-pole switch
3-pole switches the phases and leaves the neutral solid (not SDS); 4-pole switches the neutral too (SDS). The single-phase equivalent is 2-pole versus 3-poleIn: Generator grounding and bonding
32 reverse power
ANSI device 32, which trips a set that is motoring, drawing power from the bus instead of supplying itIn: Generator paralleling switchgear
4 to 1 ratio
Extension ladder base set out 1 ft for every 4 ft of working height, about a 75 degree angleIn: Portable ladder safety
4-bolt rule
1926.755 requirement that each column be anchored by a minimum of four anchor rods (anchor bolts), with a 300 lb eccentric-load strength criterionIn: Steel erection and connections
4-inch sphere rule
No opening in a required guard may pass a 4-inch sphere; 6-inch at the stair tread-riser triangleIn: Metal railing and guardrail fabrication
40 CFR 280
The federal EPA technical standards for underground storage tanks, adopted and enforced through state UST programsIn: Fuel storage tank field guide
40 percent depth
Where you drill on a slab drying from one side; 20 percent if it dries from two sidesIn: Slab moisture testing for flooring
400G / 800G ZR
OIF-defined coherent pluggables for amplified single-span DWDM, targeting roughly 80 to 120 km metro DCI; ZR+ variants extend the reachIn: Data center interconnect (DCI)
450.3
The NEC transformer overcurrent rule, sized off the transformer current, not the conductorIn: Dry-type transformer guide
4D / 5D
4D ties the model to the construction schedule for sequencing; 5D ties it to quantities and costIn: BIM VDC coordination
4PPoE
Four-pair PoE, the 802.3bt method that uses all four pairs for Type 3 and Type 4 powerIn: PoE voltage drop and heat
4X / corrosion-resistant
Type 4 plus a corrosion-rated material such as stainless, fiberglass, or polycarbonateIn: NEMA enclosure ratings
5 lb electrode (2.27 kg)
The defined-weight cylindrical probe STM7.1 uses; its contact pressure is part of the methodIn: ESD floor testing field guide
500
Constant for water, roughly 8.33 BTU/gal/degF times 60 minutes per hourIn: Hot water recirculation loops
500 psi (freeze threshold)
The commonly cited compressive strength fresh concrete should reach before it freezes, so ice no longer ruptures the pasteIn: Cold weather concreting
62 percent rule
The potential pin position, about 62 percent of the way to the current pin, where the reading is validIn: Grounding system testing field guideGround resistance testing
70V distributed audio
Constant-voltage speaker distribution where transformer taps set each speaker's power, used for many speakers over long runsIn: Intercom and paging design field guide
8 in flashing height
The commonly cited NRCA minimum height base flashing turns up above the finished roof, higher in heavy snowIn: Roof penetration flashing
8.33
BTU to raise one gallon of water 1 degree F, since a gallon weighs 8.33 lb at a specific heat of 1.0In: Water heater sizing and selection
80 percent fill / OPD
Filling to 80 percent by liquid for expansion room, enforced by the overfill prevention deviceIn: Propane LP-gas system install guide
811 / one-call
The three-digit number and the center that notify utilities to mark their lines before you digIn: Utility locating and call before you dig
811 locate / damage prevention
The one-call system and the law requiring utilities to be located and marked before any digIn: OSP fiber and FTTH construction
90-day retention
Share of new hires still employed at 90 days; a read on whether onboarding worksIn: Hiring and onboarding techs
95 / 99 / 100
Particulate filter efficiency in percent; 100 is HEPA-grade at 99.97 percentIn: Respiratory protection program guide
96.25
The constant converting GPM over square feet to inches per hour; one GPM on one square foot is 96.25 in/hrIn: Irrigation audit field guide
α
Coefficient of thermal expansion for the material, from the manufacturerIn: Pipe thermal expansion
ΔL
Change in pipe length, the movement you have to absorbIn: Pipe thermal expansion
ΔT
Temperature rise, the setpoint minus the cold inlet, in degrees F, taken on the coldest-month inletIn: Hot water recirculation loopsPipe thermal expansionWater heater sizing and selection
εr
Relative dielectric of the concrete, roughly 6 to 8 dry, higher when wet; sets the pulse velocityIn: Concrete scanning before you drill
η (eta)
Thermal efficiency factor by process: SAW near 1.0, SMAW/GMAW/FCAW near 0.8, GTAW near 0.6In: Weld heat input and CWI acceptance
ρ (rho)
Soil resistivity in ohm-meters, or ohm-centimeters in older tablesIn: Grounding system testing field guide

All glossary terms

On the job

Crews log these terms against real jobs in FieldOS, then hand the customer a clean proof page. See how FieldOS works.