ANVILFIELD Try FieldOS

Field glossary

Terms — A

318 field terms starting with A, 48 with a full reference page. Each links to the Anvilfield guides where the term is used on the job.

A
Drainage area in square feet, the roof area plus any wall area that sheds onto itIn: Gutters and downspoutsManual J load calculation field guideGrounding system testing field guideDuct leakage testing field guide
A (ps)
The cross-sectional area of the prestressing strand, about 0.153 sq in for 0.5 in strandIn: PT slab stressing
A / B
Required bearing area of a pad footing, or required width of a strip footingIn: Foundation types and footings
A and B (Abrams)
Empirical constants for a given set of materials, test method, and age; they are fit to data, not universalIn: Mix design and water-cement ratio
A and B feed
Two independent power paths to one rack, each from a separate source, for redundancyIn: Data center rack PDU typesRack readiness field guidePDU and RPP commissioning
A and B feeds
The two independent power paths to a rack, kept separate so losing one does not drop the gearIn: Data center rack cable management
A and B power
Two independent power paths to a load so either can fail with the load upIn: Data center power distribution chain
A-end / Z-end
The two terminations of a cross-connect, each needing a full location and port identifier so the circuit can be traced end to endIn: Cross-connect patch records
A-side / B-side
The isocyanate (A) and polyol resin (B) mixed 1:1 by volume at the gun to make the foamIn: SPF roof field guide
A/D director
The qualified person who directs crane assembly and disassembly under OSHA Subpart CCIn: Crane and rigging safety
a1, a2, a3
Layer coefficients: the relative strength per inch of the surface, base, and subbase materialsIn: Asphalt pavement thickness design
A2L
ASHRAE safety class for mildly flammable, lower-GWP refrigerants, with added handling and ventilation requirementsIn: Refrigerant charging field guideRefrigeration accessories field guideRefrigerant leak detection field guideRefrigerant types and A2L
A2L / CO2 / natural refrigerant
Lower-GWP refrigerants replacing HFCs: A2L blends (mildly flammable), CO2 (R-744, high pressure), and naturals like propane (R-290, flammable) and ammonia (R-717, toxic)In: Commercial refrigeration field guide
A325 / A490
The 120 ksi and 150 ksi structural bolt grades, now grades within F3125In: High-strength bolting (RCSC)
A90C
Base ampacity from NEC Table 310.16, read in the 90 degree C column for 90 degree C insulationIn: Conductor ampacity derating, NEC
A_c
Cross-sectional area of one insulated conductor, from NEC Chapter 9, Table 5, for the size and insulation actually installedIn: Conduit fill, NEC Chapter 9
A_cables
Sum of the cross-sectional areas of every cable in the tray section, in square inchesIn: Cable tray fill and copper takeoff
A_conduit
Total interior cross-sectional area of the conduit, from NEC Chapter 9, Table 4, by type and trade sizeIn: Conduit fill, NEC Chapter 9
A_total
Sum of all conductor areas in the raceway, including the neutral and the equipment grounding conductorIn: Conduit fill, NEC Chapter 9
A_usable
Inside width times usable depth of the tray, with depth capped at 6 in for the NEC fill rulesIn: Cable tray fill and copper takeoff
AA-8000 series
The modern aluminum building-wire alloy the NEC requires for most aluminum conductors, reformulated to hold a terminationIn: Aluminum branch wiring
AASHTO M288
The geosynthetic specification setting geotextile properties by application and survivability Class 1, 2, or 3.In: Geotextile separation fabric
AAV
Air admittance valve, a one-way valve that admits air under negative pressure; failure open can release gas, while failure closed can disturb drainage and trap sealsIn: Sewer gas odor field guideWet venting and common vent guideAAV and island vent guideDWV venting and pipe sizing guide
Ab
Required block bearing area against undisturbed soil, in square feetIn: Thrust restraint field guide
Abandon in place
Disconnect at both ends, de-energize, verify dead, and leave the dead wire where it isIn: Knob and tube wiring
Abandoned cable
Cable not terminated and not tagged for future use; the accessible portion must be removed under the NECIn: Cabling pathways and firestop
ABC
Automatic baseline correction, an algorithm that recalibrates a CO2 sensor by assuming its periodic low reading equals fresh outdoor airIn: IAQ monitoring and sensors field guide
ABC / positive sequence
The standard sequence; ABC, BCA, and CAB are all the same orderIn: Phase rotation and motor direction
ABC analysis
Sorting parts by movement: A items move constantly, B moderately, C rarelyIn: Service truck inventory and van stock
Abiotic stress
Damage from non-living causes such as compaction, deep planting, drought, excess water, salt, or mechanical injury, the source of most declineIn: Plant health care (PHC)
Aboveground storage tank
A storage tank installed above ground, commonly supported on a pad.In: Fuel storage tank field guide
Abrasive media (non-silica)
Garnet, slag, or steel grit/shot used to blast, in place of silica sand, which causes silicosisIn: Protective coatings and blasting
Absolute / specific humidity
Actual mass of water per mass of dry air, independent of temperatureIn: Data center humidity control
Absolute pressure
Pressure measured up from a perfect vacuum, not from atmosphere; how a deep vacuum is readIn: Refrigerant evacuation field guide
Absorption current
The slowly decaying polarization current that makes a healthy reading climb over timeIn: Insulation resistance testing field guide
Absorption distance
The duct length a steam plume needs to fully evaporate before reaching a surface or sensorIn: Humidity control field guide
AC / asphalt binder
The liquid asphalt cement that coats the aggregate, graded by PG gradeIn: Asphalt plant production
ACB / CBA / negative sequence
The reverse sequence; ACB, CBA, and BAC are all the same reversed orderIn: Phase rotation and motor direction
Acceptance criteria
The standard or value a test result is measured against to pass, from the project spec, the discipline standard, or the manufacturerIn: Quality control and the ITPAI cluster commissioningProof packet assembly
Acceptance factor
The usable expansion fraction determined from tank design and absolute-pressure relationships, including temperature correctionsIn: Expansion tank and air field guide
Acceptance volume
How much expanded water the tank can absorb between the fill pressure and the maximum operating pressureIn: Expansion tank and air field guideThermal expansion tanks
Access aisle
The marked lane beside an accessible space, part of the space, where a lift deploys; 5 ft or 8 ft wideIn: ADA accessible parking layout
Access control
Knowing and managing who is on the site through a controlled entrance, a sign-in, and a short, named after-hours key listIn: Jobsite security and theft preventionAccess control system field guide
Access floor / raised floor
The raised panel floor on adjustable pedestals over the structural slab, creating an underfloor plenum or service spaceIn: Raised access floor installationRaised floor acceptance packet
Accessible route
A continuous path from the access aisle to the entrance, no steps, max 5 percent running slopeIn: ADA accessible parking layout
Acclimation
Letting the wood reach equilibrium moisture content with the conditioned space before install, with the HVAC runningIn: Millwork and casework install
Acclimatization
The body's adaptation to heat over roughly 1 to 2 weeks of gradual exposure; lost after time away from the heatIn: Heat illness prevention
Accountable plan
An IRS-recognized reimbursement structure under which per diem and expenses stay non-taxable when properly substantiatedIn: Hours, overtime, and per diem proof
Accounts payable (AP)
The money you owe suppliers for material and services bought on account, not yet paidIn: Accounts payable and supplier management
Accounts receivable (AR)
Money customers owe you for work already completed and billedIn: AR and collections field guide
Accrual
Recognizing an expected cost in the period the related revenue is earned rather than when the cash goes out, which is the matching idea behind a warranty reserve. How it is booked is the CPA's call.In: Warranty reserve and cost management guide
Accumulator
Suction-line reservoir that protects the compressor from liquid floodback in heating and defrostIn: Heat pump fundamentals field guide
Acetylene 15 psi limit
The maximum working pressure for acetylene, which becomes unstable when compressed higherIn: Compressed gas cylinder safety
ACH
Air changes per hour, supplied air volume divided by room volume each hourIn: Ventilation rate and outdoor air field guide
ACI 318
The structural concrete code, for strength acceptance and the anchoring-to-concrete provisions in its Chapter 17In: Data center structural QA
ACI 318 / ACI 117
The structural concrete code for placement requirements, and the tolerance specification for cover and dIn: Rebar pre-pour inspection
Acid stain (reactive stain)
Metallic salts in a mild acid that react with the lime in the concrete to deposit permanent, variegated, earth-tone colorIn: Concrete coloring and staining
Acidic condensate
The weak acid a condensing appliance makes when flue-gas water vapor condenses, commonly pH 3 to 4 on gasIn: Condensate neutralizer field guide
ACR / ASCS
ACR is the NADCA standard; ASCS is the Air Systems Cleaning Specialist, the NADCA individual certificationIn: Air duct cleaning field guide
ACR copper
Air-conditioning-and-refrigeration tube, cleaned, dehydrated, and capped, sized by actual outside diameterIn: Refrigerant line sizing field guide
ACRF (ELFEXT)
Far-end crosstalk normalized to insertion loss; the older name was ELFEXTIn: Cat6A certification field guide
Action item
A single specific task with one accountable owner and a firm due date, tracked to closureIn: Progress meetings field guide
Action level
The exposure near 85 dBA over 8 hours that triggers the hearing conservation programIn: Hearing conservation and noise
Action threshold
The pest count or damage level that justifies treating; below it, you monitor and do not treatIn: Landscape IPM field guide
Activated sludge / biological treatment
The suspended-growth secondary process where microorganisms in aerated mixed liquor eat the organic waste, then settle outIn: Treatment plant systems field guide
Activation energy
The Arrhenius parameter for temperature sensitivity, often 40,000 to 45,000 J/molIn: Concrete maturity method
Active chilled beam
A beam fed with ducted primary air whose nozzles induce room air across the coil, delivering ventilation and added sensible coolingIn: Chilled beam commissioning
Active RDHx
A rear door with its own fans that draw exhaust through the coil, taking the back pressure off the server fansIn: Rear-door heat exchanger commissioning
Active vs dormant crack
Active cracks are still moving; dormant cracks have stabilized, which decides the repairIn: Concrete crack types and causes
Active vs passive DAS
Active converts RF to fiber and re-amplifies at remote units for large buildings; passive is a BDA feeding coax and antennas for smaller onesIn: DAS and public-safety radio
Active vs passive wheel
Active has a regeneration heater and dries to a target; passive (enthalpy) only recovers energyIn: Desiccant dehumidification field guide
Actuator
Electric or pneumatic motor, usually spring-return, that closes a smoke or combination damper on signalIn: Fire and smoke damper field guide
ACV vs RCV
Actual cash value is replacement cost minus depreciation; replacement cost value is the full cost to replace the roof todayIn: Storm and hail damage restoration
ADA accessible space
A space meeting the 2010 ADA Standards: 8 ft wide with a 5 ft access aisle, max 2 percent slopeIn: Striping layout and stall geometry
ADA graspability / extensions
A 1 1/4 to 2 in graspable handrail with extensions past the top and bottom nosings and returns to wall or floorIn: Metal railing and guardrail fabrication
Addendum
An issued change or clarification to a solicitation; preserve it with the bid record.In: Generator maintenance bidsDocument control field guideAs-built record drawings
Addendum log
The record of issued changes, their scope and schedule effects, and required acknowledgments.In: Find water tower painting bids
Additional charge
Refrigerant added beyond the factory charge, calculated from liquid-line length and diameter and weighed inIn: VRF commissioning field guide
Additional insured
An endorsement naming another party on your policy so your coverage defends them for your workIn: Contractor insurance and bonding
Adhesion test
A small coated patch or fabric pull tab cured and pulled to confirm the coating bonds to the substrate before the field coatIn: Roof coating restoration system
Adhesive / chemical anchor
A rod or rebar bonded into a drilled hole with structural adhesive; strength is the bond, not expansionIn: Adhesive anchor installation
Adhesive / cohesive failure
Sealant peeling off a wall versus splitting through its own bodyIn: Joint sealant replacement
Adiabatic / evaporative cooling
Using water evaporation to drop air or surface temperature and extend the free-cooling hoursIn: Data center free cooling and economizers
Adiabatic humidification
Evaporating water using the air's own heat, which cools the air as it humidifiesIn: Humidity control field guide
Adjustment factor
The more-than-three-conductor multiplier from 310.15(C)(1)In: Conductor ampacity derating, NEC
Administration
The TIA-606 discipline of identifying, labeling, and recording the cabling infrastructure so any component can be named and any link tracedIn: TIA-606 labeling and administration
Admixture
Anything besides cement, water, and aggregate added to the mix to change a propertyIn: Concrete admixtures
ADPI
Air diffusion performance index, a 0 to 100 measure of how uniform and comfortable the occupied zone isIn: Diffusers, grilles, and registers field guide
Adsorption
Water vapor adhering to the surface of the desiccant, driven by a vapor-pressure differenceIn: Desiccant dehumidification field guide
AED
Automated external defibrillator, which reads the heart rhythm and delivers a shock only if one is neededIn: Electrical shock first aid
AEGCP
Assured equipment grounding conductor program, the written OSHA program that tests and records the ground path on temporary power equipmentIn: Temporary power field guideAEGCP field guide
Aeration / dissolved oxygen (DO)
Blowers and diffusers supply oxygen to the bugs; DO in mg/L is the measured oxygen in the tank, commonly held above about 2 mg/LIn: Treatment plant systems field guide
Aerator
The screen at the tip of a faucet that mixes air into the stream and catches scale and debris; the number-one single-fixture restrictionIn: Low water pressure guide
AFCI
Arc-fault circuit interrupter, protects the building by detecting the signature of an arcing faultIn: GFCI and AFCI protection
Affected employee
A worker who operates or works near the equipment but does not perform the servicing, and who must be notifiedIn: Lockout/tagout field guide
Affinity laws
Flow scales with speed or impeller diameter, head with the square, and power with the cube of the changeIn: Hydronic balancing field guideChilled water pumping field guideCRAC/CRAH airflow setup
AFUE
Annual fuel utilization efficiency, a seasonal efficiency percentage from a standardized testIn: Gas furnace field guideCondensate neutralizer field guideBoiler types field guide
Aged binder
The oxidized, stiffened asphalt binder on RAP, harder and more brittle than fresh binderIn: Asphalt recycling and FDR
Agenda
The list of items and the purpose for a meeting, distributed ahead so people arrive readyIn: Progress meetings field guide
Aggregate base
The compacted crushed-stone layer under the asphalt that carries the load; also road base or DGAIn: Pavement base and subgrade compactionAsphalt driveway installationAggregate base and gravel roadsPaver layout and field border
Aggregate broadcast
Silica sand seeded into a wet coat for slip resistance and to take the wear of trafficIn: Traffic deck coating
Aggregate exposure (CPC class A/B/C)
How much stone the grind reveals, from cream paste (A) to salt and pepper (B) to full aggregate (C)In: Polished concrete grind and densify
Aggregate interlock
Load transfer through the rough crack faces below a tight sawcut jointIn: Control joint layout
Aggregate type (I, II, III)
ISSA gradation classes from fine to coarse that set the application rate and the duty the course can carryIn: Slurry seal and micro-surfacing
Agreement density
The share of total revenue under contract, a driver of company valuationIn: HVAC maintenance agreement guide
AHJ
Authority having jurisdiction, the official who adopts the editions, witnesses or reviews the test, and settles conflictsIn: Pavement marking and stripingPotable water disinfection guideModular data center deploymentJobsite housekeeping
AHJ / CASp
Authority having jurisdiction; Certified Access Specialist, a state-recognized accessibility inspectorIn: ADA accessible parking layout
AHJ / water authority
The local authority whose standard spec and details govern the mainIn: Thrust restraint field guide
AHRI
The body that certifies the matched indoor and outdoor combination and its ratingIn: Split-system install field guide
AHU
Air handling unit, the indoor central air handler that conditions and moves air through ductIn: Air handling unit (AHU) field guide
AI / AO / BI / BO
Analog input, analog output, binary input, binary output, the four I/O point typesIn: BAS and DDC controls field guideBMS and DDC controls commissioning
AI video analytics
Software that detects objects and conditions in the video, such as missing PPE, intrusion, or a zone breachIn: Jobsite camera and video monitoring
AIA G701
The common executed change order form that adjusts the contract sum and contract timeIn: Change order and scope control guide
AIC
Ampere interrupting capacity: the maximum fault current an overcurrent device can interrupt, a device-level ratingIn: One-line diagram field guideDistribution equipment guideUL 508A control panel and SCCRPanelboard installation
AIC / interrupting rating
The largest fault a single overcurrent device can interrupt safely, in amps or kAIn: Available fault current study
AII vs PE
Airborne infection isolation (negative, contains the patient's pathogens) versus protective environment (positive, protects the immunocompromised patient)In: Healthcare HVAC ventilation field guide
AIM Act
American Innovation and Manufacturing Act of 2020, which sets the HFC phasedownIn: Refrigerant types and A2L
Air balance
Supply outdoor air plus infiltration set against exhaust plus relief plus exfiltrationIn: Building pressurization field guide
Air barrier
A layer or system that stops air leakage through the envelope, rated by air permeance and required to be continuous and sealedIn: Building insulation and air sealingRoof vapor retarder and air barrier
Air binding
Air carried into or trapped in the pump; noisy and performance-robbing, but it does not implode and erode like cavitationIn: Pump cavitation and NPSH field guide
Air break
A waste pipe ending below the flood rim but above the trap seal, allowed for lower-hazard clear-water dischargesIn: Indirect waste and air gap guide
Air chamber
The old capped pipe stub fix that waterlogs as its air dissolves into the water and then failsIn: Water hammer arrestor guide
Air change rate
The room volume exchanged per hour, the measure of how fast the air is diluted and sweptIn: Cleanroom HVAC field guide
Air change rate (ACH)
How many times per hour the room's full air volume is replaced, the dilution rate the table sets by spaceIn: Healthcare HVAC ventilation field guide
Air clearance (PCM / TEM)
Post-work air sampling against a clearance level, PCM around 0.01 f/cc or TEM specific to asbestos, signed by an independent partyIn: Asbestos abatement procedures
Air content
Total air as a percent of concrete volume, the field-tested number judged against the specified targetIn: Air entrainment
Air curtain / air door
A unit over an opening that blows a high-velocity stream across it to separate inside from outsideIn: Air curtain field guide
Air entrainment
Deliberate creation of tiny, stable, evenly spaced air bubbles in concrete using an admixture, for freeze-thaw and deicer durabilityIn: Ready-mix ordering and deliveryConcrete driveway installationAir entrainment
Air gap
Open vertical space between the waste pipe outlet and the receptor flood rim, commonly 2x the pipe diameter with about a 1 in minimumIn: Reclaimed water and purple pipeFixtures and water efficiencyIndirect waste and air gap guideGraywater and rainwater harvesting
Air maintenance device
Regulator and restriction that tops off supervisory air or nitrogen slowly, so a real operation drops pressure faster than it refillsIn: Dry-pipe and pre-action trip test
Air mixer
A venturi that adds combustion air to propane for a clean burn; not needed for natural gasIn: Outdoor fire feature guide
Air mover
High-velocity fan that evaporates moisture from wet surfaces into the air for the dehumidifier to removeIn: Water mitigation and drying guide
Air mover vs dehumidifier
An air mover evaporates moisture off surfaces; a dehumidifier removes that moisture from the airIn: Water damage restoration field guide
Air permeance
Air leakage per unit area at a test pressure, in cfm per square foot at 0.3 in. w.c., measured by ASTM E2178 and E2357In: Roof vapor retarder and air barrier
Air separator
A fitting that separates entrained air; place it using the approved heating or cooling hydraulic arrangementIn: Expansion tank and air field guide
Air terminal
The rod or point that intercepts the strike, also called a lightning rod or strike termination deviceIn: Lightning protection (NFPA 780)
Air vent
A manual or automatic valve at each system high point that lets collected air out so the pump does not have to move itIn: Hydronic water and glycol field guide
Air voids
The percentage of air in the compacted mat; high voids let in air and water and shorten pavement lifeIn: Asphalt compaction and rollingAsphalt density testing
Air vs water-cooled
Air-cooled rejects heat to room air and needs clearance; water-cooled rejects heat to condenser water and uses more waterIn: Commercial ice machine field guide
Air-cooled vs water-cooled chiller
Heat rejected to outdoor air with a condenser coil, versus to a cooling tower through a condenser-water loopIn: Chilled water vs DX cooling
Air-entraining admixture (AEA)
The surfactant added at the plant that creates and stabilizes the entrained air, specified to ASTM C260In: Air entrainment
Air-free CO
Carbon monoxide corrected for excess air so readings compare against a target; calculated from measured CO and O2In: Combustion analysis field guide
Airflow management
Getting cold supply to every inlet and hot exhaust back to the units without the two streams mixingIn: Data center airflow management
Airside economizer
An economizer that brings filtered outdoor air into the hall or the air handlerIn: Data center free cooling and economizers
AISC 360
The Specification for Structural Steel Buildings, the design and construction standard for structural steelIn: Data center structural QA
AL / AL-CU
Connector markings for conductors the lug is listed to terminate: aluminum only, or aluminum and copperIn: Termination torque QA field guide
AL9CU / AL/CU
A connector marking meaning it is listed and tested for both aluminum and copper conductorsIn: Splices and terminations
Alarm fatigue
The state where too many false or nuisance alarms train the operator to ignore, mute, or disable the detection system, which makes the technology worthless. Fixed by tuning the detection zones.In: Proximity warning and struck-by safety tech
Alarm rationalization
Reviewing every potential alarm against an alarm philosophy so only meaningful, actionable, prioritized alarms remain, each with a documented consequence and response.In: Data center operations and the NOC
Albedo / solar reflectance
The fraction of sunlight a surface reflects; concrete is higher than dark asphaltIn: Asphalt vs concrete pavement
Alert / Action / Fire 1 / Fire 2
The rising alarm levels of a multi-stage aspirating detector, from earliest warning to the threshold that drives suppressionIn: Aspirating smoke detection
All-air / all-water / DX
The three distribution carriers: conditioned air in duct, hot or chilled water in pipe, or refrigerant in line setsIn: HVAC system types field guide
Allocated overhead
The share of company operating costs assigned to the agreement and not already counted in direct costs.In: Commercial RTU maintenance agreement pricing
Allowable range
The wider band the equipment tolerates, set by class, intended for short excursionsIn: Thermal envelope and setpoints
Allowance
A placeholder dollar amount for a specific, identified item not yet priced, such as fixtures still to be selected, reconciled to actual cost later.In: Retention and detention pond bidsPreconstruction field guideContingency and risk pricing
Allowance vs contingency
Allowance covers a known unknown; contingency covers the unknown unknownsIn: Plumbing estimating and takeoff guide
AlumiConn
The CPSC-recognized set-screw connector that joins a copper pigtail to the aluminum in a tin-plated blockIn: Aluminum branch wiring
AM
Asymmetry multiplier, for twisting away from straight aheadIn: Material handling and lifting ergonomics
AMCA 220
The test standard for air curtain aerodynamic performance; a certified rating is the credible numberIn: Air curtain field guide
Amine blush
A greasy carbamate film on curing epoxy that acts as a bond-breaker between coatsIn: Epoxy resinous floor coating install
Ammonia (NH3 / R-717)
The efficient industrial refrigerant, toxic and flammable, regulated under PSM at a large charge.In: Cold storage and refrigerated warehouse design
Amp-hour (Ah)
Battery capacity; more amp-hours means longer pump runtime at a given drawIn: Sump pump backup protection guide
Ampacity
The current a conductor carries continuously without exceeding its temperature rating, after correction and adjustmentIn: Feeder tap rules, NEC 240.21Conductor ampacity derating, NECEV feeder sizing walkthroughVoltage drop field guide
Amps
Current the load pulls, found by dividing total watts by the supply voltage, commonly 120 VIn: Commercial holiday lighting install
Anchor
The high option presented first, against which the middle option reads as the reasonable choiceIn: HVAC proposal and closing field guidePipe thermal expansion
Anchor and guide
A fixed point that holds the pipe still and the supports that let it slide lengthwise while staying in line, used to direct thermal movementIn: Pipe hangers and seismic bracing guide
Anchor bolt setting plan
The manufacturer's drawing giving the location, pattern, projection, and diameter of every anchor bolt the frames land onIn: Metal building erection
Anchor point
An engineered fixed tie-off rated to hold a fall, commonly 5,000 lb per worker or designed to a safety factor of twoIn: Rooftop permanent fall protection
Anchor profile
The peak-to-valley roughness the blast cuts into the steel, measured in mils, that the coating gripsIn: Protective coatings and blasting
Anchorage
What the system ties off to, rated at 5,000 lb per worker or engineered to a safety factor of twoIn: Roof fall protection
Anemometer
Reads air velocity in feet per minute, vane or hot-wire, converted to CFM with the free areaIn: HVAC test instruments field guide
Angle pull / U pull
Conductors change direction in the box, sized at 6x the largest raceway plus the others in the rowIn: Pull box sizing, 314.28
Angle stop
The shutoff valve on a fixture supply stub-out, trimmed with an escutcheon, that isolates the fixture for serviceIn: Fixture rough-in and setting guide
Angstrom
The length unit the coupon corrosion is measured in, one hundred-millionth of a centimeterIn: Zinc whiskers and contamination control
Annealed / tempered / laminated
Ordinary float glass that breaks in shards, heat-treated glass that breaks in pebbles, and bonded glass that holds together on an interlayerIn: Glass replacement and glazing repair
Annex B / 310.60
The NEC duct-bank ampacity figures, Annex B for low voltage and 310.60 tables for 2001 V to 35000 V; verify against the adopted editionIn: Concrete-encased duct bank field guide
Annex C
Lookup tables giving the maximum conductor count when all conductors are the same size and insulationIn: Conduit fill, NEC Chapter 9
Annual
A plant that completes its life in one growing season and is replaced rather than overwintered, the basis of color rotationIn: Seasonal color and annual rotation
Annual replacement demand
The flow of equipment replaced during a year. Estimate it from stock, installation history and a stated retirement model, then refine timing with dated equipment histories.In: Building and asset intelligence glossary
Annular gap
The space between the damper sleeve and the rated opening, sized and filled per the listingIn: Fire and smoke damper field guide
Annular space
The gap between the pipe and the edge of the opening, with a tested min and maxIn: Pipe penetration firestop guideCabling pathways and firestop
Annunciator
The panel, usually at the fire command center, that reports system trouble such as AC loss, low battery, and donor or antenna failureIn: DAS and public-safety radio
Anode / rectifier
The anode is where corrosion is directed; the rectifier is the AC-to-DC power source that drives an ICCP systemIn: Cathodic protection field guide
Anode rod
Sacrificial magnesium, aluminum, or zinc-alloy rod that corrodes in place of the steel tankIn: Water heater maintenanceWater heater typesWater heater sizing and selection
ANSI cut level (A1 to A9)
ANSI/ISEA 105 rating of glove cut resistance, A1 lowest to A9 highestIn: PPE hazard assessment and selection
ANSI device number
Two- or three-digit protective function code per IEEE C37.2In: One-line diagram field guide
ANSI device numbers
The IEEE C37.2 identifiers for relay functions: 50 instantaneous overcurrent, 51 inverse-time overcurrent, 87 differential, 27 undervoltage, 59 overvoltage, with G or N for groundIn: Coordination study field guide
ANSI/SPRI ES-1
The national test standard for low-slope roof edge systems, with the RE-1, RE-2, and RE-3 wind testsIn: Roof edge metal and coping
ANSI/SPRI RP-4
The wind design standard for ballasted single-ply roofs, turning height, exposure, slope, and parapet into a ballast designIn: Ballasted roof systems
Anteroom
A small airlock between an isolation room and the corridor that holds an intermediate pressure for a staged cascadeIn: Healthcare HVAC ventilation field guide
Anti-graffiti film
A clear sacrificial layer that takes tags and scratches so the film is replaced, not the glassIn: Commercial window film
Anti-icing
Treating dry pavement before a storm to stop snow and ice from bonding to the surfaceIn: Snow and ice management
Anti-islanding
Protection addressing unintended energization of a separated utility-system sectionIn: Data center on-site generation
Anti-oxidant compound
Joint compound applied to aluminum connections to break and exclude the oxide filmIn: Splices and terminations
Anti-passback
A rule that a credential must exit a zone before it can enter againIn: Data center physical security field guide
Anti-scald valve
An automatic compensating shower valve listed to ASSE 1016, pressure-balance, thermostatic, or combination, that holds outlet temperature when pressure shiftsIn: Fixtures and water efficiency
Anti-strip
Hydrated lime or a liquid additive that restores the binder-aggregate bond against moistureIn: Warm mix asphalt (WMA)
Antioxidant compound
Oxide-inhibiting joint compound applied to aluminum connections where required, to break and seal out the aluminum oxide filmIn: Termination torque QA field guide
Antiquing
The secondary accent color left in the grout lines and low texture, from the release or a separate tinted productIn: Stamped concrete install guide
AOS (apparent opening size)
The opening size that controls which soil particles pass, written O95; a smaller AOS retains finer soil.In: Geotextile separation fabric
APF
Assigned protection factor, the exposure reduction a respirator class is credited with; common concrete rows use APF 10, long tuckpointing APF 25In: Silica dust control methodsRespiratory protection program guide
API separator
Plain gravity oil/water separator using residence time to float free oilIn: Oil/water separator field guide
APP
Atactic polypropylene, the plastic modifier; heat and UV tolerant, almost always torch-appliedIn: Modified bitumen installation
Apparatus dew point
The effective coil surface temperature where the extended process line meets saturationIn: Psychrometric chart
Application rate
The volume of diluted material sprayed per unit area, commonly gallons per square yard, set by the product and the surfaceIn: Sealcoat and crack seal maintenanceFog seal and rejuvenator preservationSnow and ice management
Apprentice ratio
The allowed number of apprentices to journeyworkers on prevailing-wage work, set by the registered programIn: Apprenticeship and training program
Apprenticeship
A paid, earn-while-you-learn pathway combining on-the-job hours with classroom instruction, often running 18 to 48 monthsIn: Data center staffing and workforce
Approach
The difference between condensing refrigerant temperature and leaving condenser-water temperature; a rising condenser approach points to fouling or non-condensablesIn: Data center free cooling and economizersCooling tower types and operationChiller types and selectionCooling tower commissioning
Approach (tower)
Leaving condenser water minus the ambient wet-bulb; the tower cannot make water colder than the wet-bulbIn: Chiller plant sequencing optimization
Approach temperature
The gap between facility water in and coolant out at the heat exchanger; a widening approach signals foulingIn: Liquid cooling commissioningCDU commissioningImmersion cooling acceptance
Approved as noted
A review stamp allowing the work to proceed with the reviewer's markups incorporated, without a resubmittalIn: RFI and submittal process
Appurtenance
Anything mounted on the tower beyond the structure: antennas, RRUs, mounts, platforms, lines, lights, each adding load and wind areaIn: Cell tower and antenna install
APR
Annual percentage rate, the yearly cost of the loan including interestIn: HVAC customer financing guide
Apron / headwall flashing
A continuous piece run over the roofing where the top of a slope meets a wallIn: Roof flashing types
APWA color code
The national color standard for utility marks, from red electric to white proposed excavationIn: Utility locating and call before you dig
Aquifer / static water level
The water-bearing formation, and the depth to water in the well with the pump offIn: Water well drilling and well systems
AR aging
A report sorting unpaid invoices by age into current, 30, 60, 90, and 90-plus bucketsIn: AR and collections field guide
AR days (DSO)
Average days to collect after billing; days sales outstandingIn: Business KPIs and dashboard metrics
AR vs FR
Arc-rated is flame-resistant fabric that also carries a tested arc rating; all AR is FR, not all FR is ARIn: Arc flash PPE and clothingArc flash study and labels
Arbor
A small lattice-sided accent over a walk or gate, not a structure people gather underIn: Pergola and shade structure guide
Arc energy
The formula result before the process efficiency factor, what AWS practice calls heat inputIn: Weld heat input and CWI acceptance
Arc rating (ATPV / EBT)
The cal/cm2 protection value of arc-rated clothing, from the arc thermal performance value or energy of breakopen thresholdIn: Arc flash PPE and clothingArc flash study and labels
Arc reflection
TDR plus a surge, so the TDR reads the momentary arc at a high-resistance faultIn: Cable fault locating field guide
Arc-flash boundary
The distance from the gear where incident energy drops to 1.2 cal/cm2, the onset of a second-degree burnIn: Arc flash PPE and clothingArc flash study and labels
Architectural millwork
Custom non-box woodwork built for a project: trim, paneling, desks, casing, and one-off pieces, as opposed to the cabinet boxesIn: Millwork and casework install
Arcing current
The current that actually flows in the arc, lower than the bolted fault current; a method must operate at less than this to workIn: Arc energy reduction methods
Arcing ground fault
A line-to-ground arc drawing far less than the phase device trip level, which burns the gearIn: GFPE field guide
Area
Bed or lawn surface in square feet, length times widthIn: Landscape estimating and bidding
Area classification study
The qualified engineer's documented analysis that sets the class, division or zone, group, and extent for a spaceIn: Hazardous classified locations
Area divider
A raised double member on a continuous deck that relieves thermal stress by breaking a large membrane field into sections; it does not allow movementIn: Roof expansion joint installation
Area drain
A point inlet, a small grated drain at a single low spot that takes water down into a pipeIn: Subsurface drainage and French drains
Array boundary
A code-defined line a short distance outside the array, commonly 1 ft, that splits the inside and outside voltage limitsIn: PV rapid shutdown (NEC 690.12)
As-built
The marked-up set showing what was actually built, maintained as the work goes in and used to produce record drawings at closeoutIn: Document control field guideTIA-606 labeling and administration
As-built / record drawings
The drawings marked to show what was actually installed, including every field change, redlined as the work happensIn: Punch list and closeout
As-built drawing
The construction set marked by the contractor to show what was actually installed, including every field change from the designIn: As-built record drawings
As-built model
The accurate digital record of what was actually built, the foundation the twin stands onIn: Digital twin for operations
As-built verification
Overlaying the scan of installed work on the design model to find deviation, often as a heat-mapIn: Reality capture and scan-to-BIM
As-found / as-left
The recorded state of the equipment before and after the workIn: Data center MOP SOP EOP
As-left reading
The measured value recorded at the close of a test, the baseline the building is re-tested against for the rest of its lifeIn: Proof packet assembly
Asbestos / ACM
A group of fibrous minerals used in building products; asbestos-containing material is anything above the regulatory asbestos contentIn: Asbestos abatement procedures
Asbestos / NESHAP
EPA National Emission Standards for Hazardous Air Pollutants, the federal rule governing asbestos in renovation and demolition, including the survey, abatement, and notification.In: Interior demolition strip-out
Asbestos survey
A pre-work building inspection by an accredited inspector that locates, samples, and reports asbestos-containing materialIn: Asbestos abatement procedures
ASCE 7
The standard that sets design wind loads and the field, perimeter, and corner zonesIn: Single-ply attachment and windData center structural QA
ASD / VESDA
Aspirating smoke detection, the active method that draws air through sampling pipe to a high-sensitivity detector; VESDA is a common brandIn: Data center fire and life safetyAspirating smoke detection
ASHRAE 110
The tracer-gas test that proves hood containment by measuring how much tracer reaches a mannequin's breathing zone, run as-manufactured, as-installed, and as-usedIn: Lab fume hood exhaust guide
ASHRAE 15
Refrigeration safety standard driving the machine-room detector, ventilation, and reliefIn: Chiller plant startup commissioning
ASHRAE 170 / FGI
ANSI/ASHRAE/ASHE Standard 170 and the FGI Guidelines, the governing requirement for healthcare ventilation, with a space-by-space tableIn: Healthcare HVAC ventilation field guide
ASHRAE 188
The standard requiring a written water management plan for Legionella riskIn: Cooling tower commissioning
ASHRAE 241
ASHRAE Standard 241-2023, Control of Infectious Aerosols, which sets equivalent clean airflow requirements to reduce disease transmission riskIn: IAQ monitoring and sensors field guide
ASHRAE audit levels
Standard 211's three depths: Level 1 walk-through, Level 2 detailed survey, Level 3 investment-grade engineering.In: Energy audit and management field guide
ASHRAE recommended and allowable
The TC 9.9 intake envelopes; recommended is the efficiency aim, allowable is the outer limit, both at the intakeIn: Delta-T and return temperature
ASI
Architect's supplemental instruction; clarifies or makes a minor change to the contract documents without, by its terms, changing the sum or timeIn: Document control field guideAs-built record drawings
ASJ
All-service jacket, the factory facing on fiberglass that acts as a vapor retarder and protective skinIn: Pipe insulation field guide
ASME B31.1
Power Piping, for higher-pressure and higher-temperature systems such as central plantsIn: Chilled water hydro test package
ASME B31.3
The Process Piping code that governs design, materials, fabrication, examination, and testing of process pipingIn: Industrial process piping
ASME B31.9
Building Services Piping, the usual code for data center chilled-water and HVAC piping; sets the hydrostatic test at 1.5 times design pressureIn: Chilled water hydro test package
ASME Section IV
The boiler code section for heating boilers: steam to 15 psig, hot water to 160 psi or 250 degrees FIn: Boiler startup commissioning
ASME tank vs DOT cylinder
Permanent pressure-vessel tank refilled in place, versus a portable bottle filled or exchangedIn: Propane LP-gas system install guide
ASP
Available static pressure for the duct, in inches of water column, after the components are subtracted from the rated external staticIn: Manual D duct design field guide
Aspect ratio
Panel length divided by width; ACI 302.1R-15 prefers 1 to 1 and sets a maximum of 1.5 to 1 for conventional shrinkage-jointed panelsIn: Control joint layoutDuctwork types field guide
Asphalt emulsion
Asphalt carried as droplets suspended in water; it breaks and loses the water to set, with no heat needed to place itIn: Tack and prime coatSlurry seal and micro-surfacing
Asphalt recycling
Reusing the existing pavement as aggregate, binder, or a stabilized base instead of hauling it off and buying virginIn: Asphalt recycling and FDR
Aspirator
The fan inside the detector that draws the sample and whose flow the system monitors for blockages and breaksIn: Aspirating smoke detection
ASPIRE
The pipe-network modeling software for the VESDA family that calculates airflow, hole sizes, and transport timeIn: Aspirating smoke detection
ASR
Alkali-silica reaction, a slow expansive gel from reactive aggregate, alkali, and moistureIn: Concrete crack types and causes
ASSE 1010
The performance standard for water hammer arresters with a permanently sealed cushionIn: Water hammer arrestor guide
ASSE 1051 / 1050
Product standards for individual and branch type AAVs (1051) and for stack type AAVs (1050)In: AAV and island vent guide
Assembly
A bundle of the material and labor units for a repeated install, counted as one lineIn: Electrical estimating and bidding
Asset class
A defined category of physical objects sharing a useful function or counting rule. Identify the inclusions and look-alikes before searching. Preserve an unresolved category for objects the evidence does not yet classify.In: Building and asset intelligence glossary
Asset density
The concentration of relevant assets within a stated area; record the asset class, boundary, evidence date, and verification status.In: Service territory planning
Asset marking / serial registration
Engraving or stamping an ID on tools and recording serial numbers so an item is harder to fence and can be matched on recoveryIn: Jobsite security and theft prevention
Asset monitoring
Dated change detection of new, removed or altered assets.In: Asset monitoring over time
Asset Search (PorchRocket)
Asset Search is PorchRocket's custom service for finding and monitoring any asset visible from above, rather than ordering a standard property list. Searches use aerial and satellite imagery across the lower 48 and return the owner of record for each find. Use it to define a particular asset class, territory and monitoring need, then qualify the equipment and service scope in the field.In: Generator service prospect listGenerator service territory account mapCooling tower service prospecting
Asset utilization
How much an owned or rented asset is actually used versus sitting idle, used to right-size the fleetIn: Connected jobsite and RTLS
AST
Aboveground storage tank. Verify the tank's actual construction, service, and inspection basis before assigning work.In: Fuel storage tank field guideAboveground tank inspection prospectsGenerator fuel tank service opportunities
ASTM D7877
The standard guide for electronic methods of detecting and locating leaks in waterproof membranes, covering both voltage methodsIn: Electronic leak detection
ASTM D8231
The standard practice for a low-voltage electronic scanning system for detecting and locating membrane breachesIn: Electronic leak detection
ASTM E1745 Class
Grade A, B, or C by tensile strength and puncture resistance; all classes are 0.1 perms or lessIn: Under-slab vapor barrier and slab moisture
ASTM F1487
The consumer safety performance specification for public playground equipment, ages 2 through 12In: Playground safety surfacing
ASTM F2200
The construction standard for the gate itself: openings, screening, exposed edges, and restraintsIn: Automatic gate operator field guide
ASTM F3125
The consolidated bolt specification carrying A325, A490, F1852, and F2280 as gradesIn: High-strength bolting (RCSC)
Aterm
Ampacity in the column matching the lowest-rated termination, usually 75 degrees C, per NEC 110.14(C)In: Conductor ampacity derating, NEC
Atmospheric / Category I
A gas unit that takes combustion air from the room and vents by natural draft up a vertical flueIn: Unit heater field guide
ATP verification
Swab-and-luminometer test measuring adenosine triphosphate as organic residue in relative light units, to confirm cleaning was effectiveIn: Biohazard and trauma cleanup guide
ATS
Automatic transfer switch, which senses the loss of normal power and moves the load to the alternate sourceIn: One-line diagram field guideData center power distribution chainStandby generator installGenerator acceptance and turnover
Attached ledger
The bolted and flashed board that fastens an attached structure to the house, the same connection as a deck ledgerIn: Pergola and shade structure guide
Attachment / anchoring system
A wet-glaze structural-silicone bead or a mechanical batten that ties the film edge to the frame so it resists, not just holds shardsIn: Commercial window film
Attic stock
The specified spare materials handed to the owner at closeout: tiles, lamps, filters, paint, keys, and the likeIn: Punch list and closeout
ATU / mound / pressure dosing
Alternative methods for poor sites: an aerobic treatment unit adds oxygen for higher treatment, a mound builds the field up in sand, pressure dosing pumps even timed doses to the fieldIn: Septic system field guide
Audio / wiretap consent
The legal requirement to obtain consent before recording audio, one-party or all-party depending on jurisdictionIn: Jobsite camera and video monitoring
Authorized employee
The worker who applies the lockout and performs the servicing on the equipmentIn: Lockout/tagout field guide
Authorized scope
What the customer agreed to pay for, captured before the workIn: Work order management field guide
Automated irrigation / fertigation
The drip and recirculation that water the wall on a schedule, and the nutrient feed delivered through that waterIn: Living wall and green wall systems
Automatic gate operator
The powered motor and controller that opens and closes a gate on command, listed to UL 325In: Automatic gate operator field guide
Automatic isolation valve
An actuated valve that closes on detection to stop the flow and isolate the affected loop or rack in secondsIn: Liquid-cooling leak detection
Automatic transfer switch (ATS)
Equipment that transfers a load between power sources; list its service tasks separately.In: Generator maintenance bidsGenerator service prospect list
Autonomous / machine-control equipment
Earth-moving equipment guided to a design surface by GPS, either semi-autonomous with an operator in the cab or fully autonomous with noneIn: Construction robotics
Autonomy
Battery runtime in minutes carrying the load, verified at design loadIn: UPS and STS commissioning hold points
Autonomy / ride-through
How long the energy store carries the load before the generator doesIn: UPS topology and redundancy design
Autotransformer
A transformer with primary and secondary electrically tied, sharing a winding, so it does not isolateIn: Buck-boost transformer guide
Auxiliary / emergency heat
Backup heat on a heat pump; aux stages in automatically, emergency forces it and locks out the compressorIn: Heat pump fundamentals field guideThermostat types and wiring field guide
Auxiliary gutter
A covered trough supplementing equipment locally, NEC Article 366, commonly limited to about 30 ft beyond the gearIn: Wireway and gutter field guide
Availability
The fraction of time or producible energy the plant was able to operate rather than sitting on a faultIn: Solar PV O&M field guide
Availability / MTTR
Availability is the percent of time the load was up, quoted in nines; MTTR is mean time to repair or recover, how fast operations restores after a failure.In: Data center operations and the NOC
Available fault current
The maximum fault current available at the equipment; interrupting and short-circuit current ratings must be at least equal to itIn: Service and panel upgradeOvercurrent protection guideUL 508A control panel and SCCRSelective coordination field guide
Available fault current (AFC)
The current a bolted fault can draw at a point, set by the utility, transformer, conductors, and motorsIn: Available fault current study
Available flow
What the meter, service line, and working pressure can actually deliver at the point of connectionIn: Drip irrigation design and install
Available static pressure
Pressure available for duct friction after subtracting applicable external component losses at the design airflowIn: External static pressure field guide
AVB
Atmospheric vacuum breaker; the simplest device, back-siphonage only, no continuous pressure, no downstream valve, non-testable (ASSE 1001)In: Backflow assembly types
Average ticket
Revenue per completed job; rises when good-better-best options are presentedIn: Flat-rate pricing price bookHVAC proposal and closing field guide
Averaging beam
A long ski reference that filters short bumps to smooth the rideIn: Asphalt milling and cold planing
AVR
Automatic voltage regulator, which holds alternator voltage and is only fully tested under a reactive loadIn: Generator load bank testing
AWG
American Wire Gauge; the smaller the number, the larger the conductor and the allowanceIn: NEC box fill, 314.16PoE voltage drop and heat
AWG / kcmil
American Wire Gauge for smaller sizes, thousand circular mils for conductors above 4/0In: Conductor types and insulationConductor ampacity derating, NECVoltage drop field guide
AWI / AWS grade
The Architectural Woodwork Institute quality grade, Economy, Custom, or Premium, setting materials, joinery, tolerances, and finish; now paired with a separate duty level, 1 to 4In: Millwork and casework install
AWWA D102
The AWWA standard for coating the inside and outside of steel water-storage tanksIn: Tank coating and lining
AXT (ANEXT / AFEXT)
Alien crosstalk between adjacent cables in a bundle, near-end and far-endIn: Cat6A certification field guide
Az
Net occupiable floor area of the zone, in square feetIn: Ventilation rate and outdoor air field guide

All glossary terms

On the job

Crews log these terms against real jobs in FieldOS, then hand the customer a clean proof page. See how FieldOS works.