ANVILFIELD Try FieldOS

Field glossary

Terms — N

147 field terms starting with N, 22 with a full reference page. Each links to the Anvilfield guides where the term is used on the job.

N / N+1 / 2N
Redundancy levels, from no spare, to one extra component, to two full independent systemsIn: Data center buildout phasesData center tier classification
N / R / P filter
Particulate filter oil resistance: N not oil-resistant, R oil-resistant, P oil-proofIn: Respiratory protection program guide
N per 1000 sq ft
Pounds of actual nitrogen per thousand square feet, the turf fertilizer unitIn: Commercial maintenance program
N+1
One more cooling unit than the row needs, so any single unit can drop and the survivors still hold the inletsIn: CDU commissioningUPS topology and redundancy designIn-row cooling commissioning
N+1 / 2N
One spare unit beyond the need, or two full systems each carrying the whole load, the common redundancy arrangementsIn: Liquid cooling concurrent maintainabilityPower density and capacity planning
N+1 redundancy
One fan more than the design airflow needs, so any single failure still meets designIn: Fan array (fan wall) field guide
N, N+1, 2N
Redundancy notations: just enough, one spare, and two full independent systemsIn: Data center power distribution chain
N-P-K
Percent by weight of nitrogen, available phosphate, and soluble potash on the bag, in that orderIn: Turf fertilization and soil testing
N<sub>awg</sub>
Number of counted conductors of a given wire sizeIn: NEC box fill, 314.16
n_c, L_c
Count of mated connector pairs and the per-pair loss allowance in dBIn: Fiber splice loss budget
N_drops
Number of drops in the zone, from the panel schedule and rack elevationsIn: Cable tray fill and copper takeoff
n_s, L_s
Count of splices and the per-splice loss allowance in dBIn: Fiber splice loss budget
NAC
Notification appliance circuit, the power circuit feeding horns and strobesIn: Fire alarm install and test
NADCA Vacuum Test
Gravimetric post-cleaning test measuring debris left on the cleaned surface against the standard limitIn: Air duct cleaning field guide
Nail line / nail zone
The marked band where nails go, so each fastener holds two courses; nails above or below it failIn: Steep-slope shingle roofing
Nail sickness
Widespread loss of slates when corroded original fasteners fail, even though the slate itself is soundIn: Slate roof field guide
Nailable deck
A deck that accepts fasteners; some only with special auger or base-sheet fastenersIn: Roof deck substrate types
Nailer
Continuous perimeter wood blocking the edge metal and cleat fasten into, part of the wind load pathIn: Roof edge metal and coping
Nameplate kVA
The unit's isolation rating, much smaller than the load it supports in the buck-boost connectionIn: Buck-boost transformer guide
Nameplate rating
The manufacturer's worst-case maximum draw, well above the actual measured loadIn: Power density and capacity planning
Nameplate vs actual
Nameplate is the worst-case maximum draw; actual is the measured load, commonly a fraction of nameplateIn: Stranded capacity and power utilizationPower capping and oversubscription
Natatorium
An indoor swimming pool and the room enclosing it, treated as a contained, controlled environmentIn: Natatorium HVAC field guide
NATE
North American Technician Excellence, the recognized voluntary HVAC competency credentialIn: Hiring and onboarding techsApprenticeship and training program
Nativar
A cultivar of a native species; wildlife value varies and some offer less pollen and nectar than the straight speciesIn: Native and pollinator planting
Native plant
A species that occurred in an area before widespread human introduction, judged at the ecoregion scale, not the countryIn: Native and pollinator planting
Native vs adapted
Native plants grew in the region naturally; adapted plants are non-natives that thrive locally without becoming invasiveIn: Xeriscape and drought-tolerant designLandscape design and plant selection
Natural frequency
The rate the equipment-on-mount system bounces at; kept well below the operating speedIn: HVAC vibration isolation field guide
Natural slate
Roofing shingles split from quarried metamorphic stone, as opposed to molded synthetic or composite slateIn: Slate roof field guide
NC
Noise criterion, a single-number rating of a device's sound level used to hold it under a room limitIn: Diffusers, grilles, and registers field guide
NDE / radiography
Nondestructive examination of welds (VT, PT, RT, UT); radiography is the x-ray or gamma volumetric methodIn: Industrial process piping
Ndesign
The design gyration count, set by traffic, where the mix is held to 4 percent air voidsIn: Asphalt mix design (Superpave)
NDIR
Nondispersive infrared, the method good CO2 sensors use to measure carbon dioxide directly by infrared absorptionIn: IAQ monitoring and sensors field guide
NDL warranty
No Dollar Limit warranty: the covered repair obligation has no monetary cap, subject to the issued warranty's scope, exclusions and owner dutiesIn: Roof asset managementRoof warranty types and NDLSingle-ply seam QARoof maintenance program
Near-miss
An event that could have caused injury but did not; a free lesson that feeds back into the JHA and the talkIn: Incident investigationJHA, toolbox talks, pre-task planning
NEBB / AABC
The bodies that publish TAB procedural standards, report forms, and the firm and technician certificationsIn: Air balancing report field guide
NEC 110.14(D)
The code section requiring terminations to be tightened to the manufacturer's value, with a calibrated torque tool or approved means where a value is givenIn: Termination torque QA field guide
NEC 242
The NFPA 70 article governing overvoltage protection and SPDs, formerly Article 285In: SPD installation field guide
NEC 645
NFPA 70 Article 645, the optional rules for information technology equipment rooms; 645.10 is the disconnecting-means (EPO) sectionIn: EPO testing field guide
NEC 700 / 701 / 702
Emergency, legally required standby, and optional standby articles that set the transfer-time class and the wiring rulesIn: Standby generator installATS commissioning field guide
NEC 706 / 705
The NEC articles for energy storage systems (706) and for interconnection to the utility supply (705)In: Battery energy storage (BESS)
NEC Article 555
The National Electrical Code article governing marina and dock electrical, written to keep leakage current out of the waterIn: Boat dock and marina construction
NEC Article 625
The NEC article governing EV supply equipment, including the continuous-load and disconnect rulesIn: DC fast charging station design
Neck vs face velocity
Air speed in the inlet collar (neck, the noise source) versus across the visible face after spreadingIn: Diffusers, grilles, and registers field guide
Negative air / dust containment
Sealing the work area with poly and zip walls and holding it below surrounding pressure with HEPA negative-air machines so dust stays in the work zone.In: Interior demolition strip-out
Negative float
A signal the work is behind: the calculated finish lands past a deadline by that many daysIn: Construction scheduling field guide
Negative pressure
Lower air pressure inside the containment than around it, so any leak pulls inward, not outIn: Mold remediation field guide
Negative pressure room
A room held below its surroundings so air flows in, protecting everyone else from the patient (AII)In: Healthcare HVAC ventilation field guide
Negative side
The interior, dry face; used when the exterior cannot be reachedIn: Below-grade waterproofing
Negative space pressurization
Keeping the pool room at lower pressure than adjacent spaces so its humid, corrosive air stays in rather than spreadingIn: Natatorium HVAC field guide
Negative-air machine
HEPA-filtered vacuum unit that holds the system under continuous negative pressure during cleaningIn: Air duct cleaning field guide
Negative-pressure enclosure
A sealed poly containment held below surrounding pressure by HEPA negative-air machines so leakage flows inwardIn: Asbestos abatement procedures
Neher-McGrath
The 1957 calculation method behind engineered duct-bank ampacity and the NEC Annex B and 310.60 figuresIn: Concrete-encased duct bank field guide
NEMA 250
The standard that defines enclosure types and what each protects againstIn: NEMA enclosure ratings
NEMA 3R
A raintight enclosure rating for outdoor use, keeping rain and sleet out with a path to drain condensationIn: Wireway and gutter field guide
NEMA enclosure type
The rating for where an enclosure may go: 1 indoor, 3R outdoor, 4/4X wet or corrosive, 7 hazardous, 12 dustyIn: Disconnect switch types and requirements
NEMA load class
A tray's working load per foot on a given span: class A 50 lb/ft, B 75 lb/ft, C 100 lb/ft, per NEMA VE 1In: Cable tray fill and copper takeoff
Neocloud / GPUaaS
A specialist operator renting GPU capacity as a service for AI and HPC workloadsIn: Data center types field guide
NESHAP
EPA National Emission Standards for Hazardous Air Pollutants, the federal rule that governs asbestos in renovation and demolition, including the survey, abatement, and notification.In: Building demolition planning
NESHAP / AHERA
EPA NESHAP (40 CFR 61 Subpart M) governs emissions, notification, and waste; AHERA governs asbestos in schoolsIn: Asbestos abatement procedures
Net 30 / net 60
Full amount due in 30 or 60 days, an interest-free loan from the supplier for that termIn: Accounts payable and supplier management
Net depth
The depth the plants need for the period after subtracting effective rainfallIn: Irrigation controller programming
Net free area
The actual open area through a grille or louver, smaller than the nominal opening sizeIn: Water heater venting and combustion airSteep-slope shingle roofing
Net free area (NFA)
The actual open airflow area of a vent after screen and louver, rated in square inchesIn: Roof attic ventilationFascia, soffit, and eave trim
Net need
The depth in inches the plants require for the period after subtracting effective rainfallIn: Irrigation audit field guide
Net pressure
Discharge pressure minus suction pressure, the pressure the pump itself added and the value plotted on the curveIn: Fire pump acceptance test
Net profit
What is left after overhead comes off gross margin; the company's true profitIn: Business KPIs and dashboard metrics
Net terms / due on receipt
When payment is due; Net 30 means 30 days from invoice, due on receipt means when sentIn: AR and collections field guide
NETA ATS
Acceptance Testing Specifications, the standard for field acceptance tests on electrical power equipmentIn: Data center power commissioning
NETA MTS
ANSI/NETA Maintenance Testing Specifications, the reference for in-service test methods and valuesIn: MV switchgear maintenance and testing
NETD
Noise-equivalent temperature difference, a measure of camera thermal sensitivity; it does not establish absolute temperature accuracyIn: Infrared thermography field guide
Neutral (grounded)
The return conductor; lands on the silver screw, never on the greenIn: Device wiring: receptacles and switches
Neutral bonding
The neutral-to-ground connection, made in exactly one place; a second bond puts neutral current on the grounding conductorIn: Generator interlock and backfeed safety
Neutral load
The maximum unbalanced load the neutral carries, sized under 220.61In: Load calculation, NEC 220
Neutral pressure plane
The height in a building where inside and outside pressure are equalIn: Building pressurization field guide
Neutralization
Bringing the waste pH into the dischargeable range before it joins the sanitary sewerIn: Special waste and acid neutralization
Neutralizer
Media that raises the pH of acidic condensing-appliance condensate before disposalIn: Condensate drain and trap field guide
Neutralizing
Stopping the acid reaction and lifting residue with a baking soda or ammonia solution, then rinsing clean before sealingIn: Concrete coloring and staining
Neutralizing amine
A chemical that travels with the steam and neutralizes carbonic acid in the condensate returnIn: Boiler water treatment field guide
Neutralizing media
Calcium carbonate (limestone, marble, calcite) or magnesium oxide that reacts with the acid and raises pHIn: Condensate neutralizer field guide
NEVI uptime
The federal corridor requirement that each port average over 97 percent uptime on a rolling 12-month basisIn: DC fast charging station design
NEXT / PSNEXT
Near-end crosstalk between pairs, and the power-sum from all pairs at the near endIn: Cat6A certification field guide
Next upstream manhole
The public-sewer manhole whose cover elevation sets the code trigger for protecting lower fixturesIn: Backwater valve field guide
NFPA 110 Class
The runtime classification, the minimum hours the plant runs at rated load without refueling, such as Class 72In: Generator fuel system and day tank
NFPA 13
The standard for the installation of sprinkler systems; 13R covers low-rise residential, 13D covers one- and two-family dwellingsIn: Fire sprinkler system design guide
NFPA 20 / 14
The standards for the fire pump and the standpipe and hose system, respectivelyIn: Fire pump and standpipe guide
NFPA 20 / NFPA 25
NFPA 20 governs the installation and the acceptance test; NFPA 25 governs the recurring inspection, testing, and maintenanceIn: Fire pump acceptance test
NFPA 58
The LP-Gas Code, governing the container, placement, regulators, and storageIn: Propane LP-gas system install guide
NFPA 70E
The NFPA standard for electrical safety in the workplace; the program, boundaries, PPE, permit, and label rulesIn: Arc flash study and labels
NFPA 855
Installation standard for stationary energy storage systems, applied through the applicable codes and project requirementsIn: Battery energy storage (BESS)Rack BBU and ride-through
Nip point
The in-running pinch where a belt meets a pulley, a chain meets a sprocket, or two rollers meet, that draws in and amputatesIn: Conveyor system installation
Nipple
Raceway 24 in or less between enclosures, allowed 60 percent fill and exempt from the more-than-three deratingIn: Conduit fill, NEC Chapter 9
Nitrogen purge
A low flow of dry nitrogen through the tube during brazing to displace oxygen and prevent internal oxide scaleIn: Refrigerant line brazing field guideMedical gas piping field guide
NLC / LLLC
Networked lighting control, and luminaire-level control with a sensor in every fixture, rebate-eligible on the DLC listIn: Lighting controls and dimming
NLGI grade
Grease consistency scale; NLGI 2 is the common soft-solid motor gradeIn: Motor bearings and shaft grounding
NMAS
Nominal maximum aggregate size, one sieve above the first to retain over 10 percent; names the mix and sets the liftIn: Asphalt compaction windowAsphalt mix types by layerAsphalt mix design (Superpave)Asphalt mill and overlay
NMAS / t/NMAS
Nominal maximum aggregate size, and the lift-thickness-to-NMAS ratio that sets minimum liftIn: Asphalt compaction window
NMC
Lithium nickel manganese cobalt oxide: higher energy density, less thermally stable than LFPIn: Rack BBU and ride-through
No-load tap
Primary voltage-adjustment tap set with the unit de-energized, commonly 2.5 percent stepsIn: Dry vs liquid transformer guide
No-load taps
Off-load primary connection points, commonly plus or minus 5 percent in 2.5 percent stepsIn: Dry-type transformer guide
NOAEL / LOAEL
No-observed and lowest-observed-adverse-effect levels, the human-exposure limits the design concentration is held againstIn: Clean agent room integrity
NOC
Network operations center, the team and room that watch the IT and network layer, server and link health and service availability, as distinct from the physical plant.In: Data center operations and the NOC
Nominal max aggregate
Largest standard sieve size; coarse aggregate over 1-1/2 in is wet-sieved out before a slump testIn: Concrete slump test
Nominal max aggregate size
The largest standard sieve the coarse aggregate is graded to; drives water demand and member fitIn: Mix design and water-cement ratio
Non-chloride accelerator
A set accelerator without chloride, used in reinforced and post-tensioned concrete to avoid corroding the steelIn: Concrete admixturesCold weather concreting
Non-combustible cabinet
A structure of masonry or galvanized steel stud with cement board, not wood, that carries the counter and resists heat and weatherIn: Outdoor kitchen construction guide
Non-condensable
A gas such as air that will not condense in the system, raising head pressure until the vacuum removes itIn: Refrigerant evacuation field guide
Non-condensable gas
Air or other gas that leaks into a two-phase system and blankets the condenser, degrading heat rejectionIn: Two-phase cooling
Non-condensables
Air and moisture in the refrigerant circuit that blanket condenser tubes and raise condensing pressure and liftIn: Centrifugal chiller surge controlRefrigerant evacuation field guide
Non-conformance report (NCR)
The document recording work that failed the spec, tracked through disposition, root cause, and close-outIn: Quality control and the ITP
Non-entry rescue
Retrieving an entrant from outside the space with a harness, retrieval line, and tripod or davit winch, with no one enteringIn: Confined space entry field guide
Non-friable
Bound material that cannot be crumbled by hand when intact, split into Category I and II; releases fibers when cut, ground, or brokenIn: Asbestos abatement procedures
Non-penetrating support
A block, sleeper, or stand that carries load on top of the membrane without piercing itIn: Rooftop equipment supports and walkways
Non-potable
Water not safe or approved for drinking, covering reclaimed, graywater, and rainwaterIn: Reclaimed water and purple pipe
Non-self-supporting ladder
A ladder that leans on a structure for support, such as a single or extension ladderIn: Portable ladder safety
Non-shrink grout
Grout built so controlled expansion offsets shrinkage, holding contact under a plate; ASTM C1107In: Precast erection and connectionsGrout types and baseplate groutingAnchor bolt and baseplate grout QA
Non-shunted tombstone
A lamp holder whose two contacts are not internally connected, required by most Type B tubesIn: LED lighting retrofit
Non-stock / special-order
A part ordered for a specific job rather than held on the truckIn: Service truck inventory and van stock
Noncoincident loads
Loads that cannot run at once, such as heat and AC, where only the larger is counted (220.60)In: Load calculation, NEC 220
Noncondensables
Gases such as air that will not condense in the system, raising head pressure until evacuated outIn: Refrigerant leak detection field guide
Nonconformance report (NCR)
The formal record of work or material that does not meet the requirement, tracked through disposition and corrective action to closureIn: Construction QA/QC program
Normally-open / normally-closed
The damper's position with no power, which sets how it failsIn: HVAC zoning systems field guide
Not-to-exceed (NTE)
A cap on time-and-material billing that the contractor cannot pass without further approvalIn: Change order and scope control guide
Notched wedge
A tapered longitudinal joint with top and bottom notches, formed on the first pass to confine the edge and raise densityIn: Longitudinal joint density
Notched wedge joint
A longitudinal joint with a tapered, notched edge that tends to compact more uniformly than a butt jointIn: Asphalt paving inspection
Notched-wedge joint
A tapered longitudinal joint with small top and bottom notches, formed by a screed shoe to confine the first pass edge and densify the seamIn: Longitudinal joint densityAsphalt paving joints and handwork
Notice of intent
A written warning that you will record a lien if the bill is not paid by a stated date; required in some states and a common collection tool.In: Mechanics lien and preliminary notice
NOWL
Normal operating water level on a steam boiler; the LWCO trips a set distance below it while water still covers the metalIn: Boiler startup commissioning
NPDES discharge
A permitted discharge of water to surface waters under the federal pollutant discharge programIn: Construction dewatering field guide
NPDES permit / SDWA
The NPDES discharge permit governs wastewater effluent under the Clean Water Act; the Safe Drinking Water Act sets MCLs for drinking waterIn: Treatment plant systems field guide
NPS Preservation Brief 2
The National Park Service guidance on repointing mortar joints in historic masonry buildingsIn: Masonry repointing and restoration
NPSH
Net positive suction head; available (NPSHa) must exceed required (NPSHr) at the suction to avoid cavitationIn: Pump station sizing
NPSH margin
The cushion NPSHa is held above NPSHr; set per the manufacturer and the application, not a fixed numberIn: Pump cavitation and NPSH field guide
NPSHa
Net positive suction head available; the suction-side pressure margin the system delivers, above the water's vapor pressure, in feetIn: Pump cavitation and NPSH field guideHydronic pump install field guide
NPSHa / NPSHr
Net positive suction head available from the system versus required by the pump; NPSHa must exceed NPSHr or the pump cavitatesIn: Hydronic pump install field guide
NPSHr
Net positive suction head required; the suction head the pump needs at a given flow, read from the manufacturer's curveIn: Pump cavitation and NPSH field guideHydronic pump install field guide
NPT
National pipe thread, the tapered thread sealed with PTFE tape or pipe dope, not by the threads aloneIn: Pipe joining methods
NRC vs CAC
NRC is sound absorbed in the room; CAC is sound blocked from passing over a partition into the next roomIn: Suspended acoustical ceiling field guide
NRR
Noise Reduction Rating on hearing protection, a lab figure that is derated for real-world useIn: PPE hazard assessment and selectionHearing conservation and noise
NSF listing
Certification that foodservice equipment meets the NSF/ANSI sanitation standards for cleanable, food-safe construction, which the health code commonly requiresIn: Kitchen equipment install field guide
NSF/ANSI 53
Certification for point-of-use filters that reduce lead, both soluble and particulateIn: Lead service line guide
NSF/ANSI 61
The certification that a material in drinking-water contact does not leach contaminants above health limitsIn: Tank coating and liningLead service line guide
NSPS Subpart IIII
40 CFR Part 60 Subpart IIII, the federal standard for stationary CI enginesIn: Generator emissions and permitting
NTE (not-to-exceed)
The cost cap a customer sets before fresh approval is requiredIn: Work order management field guide
NTEP
National Turfgrass Evaluation Program, the independent multi-state cultivar trials since 1981In: Turfgrass selection
NVP
Nominal velocity of propagation; how the tester converts signal time into lengthIn: Cat6A certification field guide
NVR / VMS
NVR is a dedicated recording appliance for small to mid sites; VMS is server or cloud software that scales and integrates with other systemsIn: CCTV system design field guide

All glossary terms

On the job

Crews log these terms against real jobs in FieldOS, then hand the customer a clean proof page. See how FieldOS works.